PROJECT UPDATES

Sesha Mews

By Michael Hughes
Red East has been working extremely hard on the installation of the services and infrastructure at Sesha . The main sewer lines have been completed . This entailed digging and laying pipes for over 1.6km and digging trenches over 2.5m deep . The domestic water reticulation has been completed and the lines have been pressure tested and signed off by the engineers . The stormwater lines are currently being installed and can be seen exposed in the accompanying photograph . Currently we have just started excavations on the show house and an additional 11 houses . Sales have been fairly good so far with 11 houses currently under construction and 17 more houses sold , but waiting for bond approval .
Developer : Architect :
Time Projects
Time A & PM and Paul Munnik Architects
Civil & structural engineer : Bergstan Consulting Quantity surveyor : Electrical engineer : Main contractor :
Time A & PM Scales Red East

Motswedi Place

By Roy Mapharing
Motswedi Phase 1 of the development is visibly coming to completion with only six weeks to go . Currently , we are completing the final touches on the kitchens , built-in cupboards installations , landscaping , fixing snags , interior and exterior finishes . Registration of the sectional title is also ongoing . Phase 2 of the development is also progressing well and we are currently working on the second fix for electrical , plumbing and wall finishes . Motswedi sales have been very impressive - Phase 1 and Phase 2 are currently 95 % sold .
STAFF NEWS

Congratulations

There is some life in the old bones with Turnie Morolong running the 10km and Chevon Barrowman running the 5km races in The SPAR Community Challenge on 19 August . The proceeds from this 10-part running series are donated to charity .
ISSUE 55 - SEPTEMBER 2023 5