WVUSD: 2019/2020 Year-End Results
• Maple Hill Elementary School
Non-Bond Projects
o Slurry seal/stripe parking lots and playgrounds summer 2020
o Replaced wood siding at existing ball wall
o Replace fabric on shade structures
Bond Projects
o Completed installation of security cameras
• Quail Summit Elementary School
Non-Bond Projects
o Completed installation of new sound system in MPR
o Resurface existing parking lots, slurry seal/stripe playgrounds summer 2020
o Installed new motorized projection screen in MPR
o Clean and fireproof stage drapes
Bond Projects
o Completed installation of security cameras
• Vejar Elementary School
Non-Bond Projects
o Completed installation of new sound system in MPR
o Added 4’ wide of concrete at existing sidewalks – rooms 16, 17, 18, 22, 23, 24, and 25
o Slurry seal/stripe parking lots and playgrounds summer 2020
o New restroom building in DSA for approval
o Installed new seating wall and concrete in front of school
o Renovate existing portable to new kindergarten classroom – room 6
o Add new office in existing classroom – room 9
Bond Projects
o Completed installation of security cameras
o New staff parking lot and parent drop off in DSA for approval
38