WINDOWS Magazine Spring 2017 | Page 18

EDITORIAL | LEGAL DAMAGES FOR BREACH OF CONTRACT – A QUICK GUIDE The purpose of an award of damages is to put the injured party in the position that they would have been in had the contract been performed. In building contracts, damages mainly arise from defective work, incomplete work and failure to complete work on time. BRYAN PICKARD Greenhalgh Pickard Solicitors and Accountants W hen a party breaches a contract the innocent party has a right to recover damages. This right does not depend on any contract term. It is a common law right. The right to damages arises when there is a breach of the contract not when the damage occurs. For example, where a window is not watertight the actual damage will not occur until it rains and water enters the building. While there may not be any damage until this happens, the right to damages arises from when the window was installed not when the damage occurred. The recovery of damages requires proof of the contract and of the breach. The fact that damages may be difficult to assess does not prevent it being claimed where there is a breach of contract. Where there is no loss or minimal loss, an innocent party can be awarded nominal damages, for example, $2. In general, parties may agree to exclude or limit damages by terms in the contract. However, in some contracts, legislation may prohibit terms which exclude or limit liability. For example, consumer contracts and terms that exclude consumer guarantees implied by the Australian Consumer Law. The amount or quantum of damages in the first instance will be the loss or damage that arises naturally or the usual course of things from the breach, for example, the cost of making a window waterproof. It can also extend to damage that can ordinarily or reasonably be contemplated by the parties at the time they entered into the contract, for example, water damage in a building. Where a party makes it known that there are special circumstances before entering into the contract this may also be included in damages, such as loss of rent if the building cannot be occupied. In building contracts, the usual damages an innocent party may recover is the cost of rectification of the defective work. This may include demolition and rebuilding if the work is reasonable and necessary. They can also recover other costs such as loss of rent, relocation costs and consultant fees. In very limited circumstances where rectifying defective work is an unreasonable course to adopt, an injured party may not be able to recover the cost of rectifying the defect. Instead, they may be able to recover any loss of the value of the building and where no loss in value, the loss of enjoyment and/or inconvenience in using the building. In building contracts, damages for defective work are usually limited by terms requiring a contractor to rectify defective work. However, the failure of a contractor to do this allows the other party to engage another contractor to complete the work. If this work costs more than the price of the contract with the first contractor, the other party can recover this cost as damages. The amount of damages will be the cost of the work that is reasonable and relevant to put the other party in the same position as if the contract had been carried out. Where there has been a breach of contract, the injured party must take reasonable steps to minimise the effects of the breach. For example, with a leaking window, the owner has a duty to take reasonable steps to minimise the effect of water entering the building. Mitigation of damage not does require a person to do what is unreasonable, or may be a serious risk to their interests. Nor are they under a duty to do what they cannot afford. In bringing a claim for damages there is a once and for all rule. What this means is that damages are awarded only once for any cause of action, for past, present and future losses flowing from the breach of contract on which the action is taken. Once damages have been awarded, you cannot return to the court at a later time and ask for additional damages for further losses that may have occurred or been discovered. Liquidated damages clauses are frequently found in building contracts. They are designed to avoid litigation about the sum to be awarded in the event of default. To be enforceable, a liquidated damages clause must be a genuine pre-estimate of the loss that would be caused by a particular breach. However, where the amount specified is more than a reasonable amount arising from the loss, it is regard as a penalty and unenforceable. For more information, contact Greenhalgh Pickard Solicitors and Accountants on 07 5444 1022 or visit www.greenhalghpickard.com.au 16 Spring 2017