Standard Project Report 2016
|  Outcome |  Project End  Target |  Base Value |  Previous  Follow-up |  Latest  Follow-up | 
 Ownership and capacity strengthened to reduce undernutrition and increase access to education at regional, national and community levels
 NCI: School Feeding National Capacity Index
 BHUTAN, Project End Target: 2018.12, Stakeholders consultation workshop, Base value: 2014.12, Joint survey, Stakeholders consultation workshop, Previous Follow-up: 2015.12, Joint survey, Stakeholders consultation, Latest Follow-up: 2016.12, Joint survey, Stakeholders consultation
 > 14.00 11.00 12.00 12.00
 Hand-over strategy developed and implemented [ 1 = not achieved; 2 = partially achieved; 3 = achieved ]
 BHUTAN, Project End Target: 2018.12, Base value: 2013.12, WFP programme monitoring, Previous Follow-up: 2015.11, WFP programme monitoring, Latest Follow-up: 2016.12, WFP programme monitoring
 = 3.00 2.00 2.00 2.00
 Output Indicators
 Output Unit Planned Actual
 % Actual vs. Planned
 SO4: Capacity Development- Strengthening National Capacities
 Number of government / national partner staff receiving technical assistance and training individual 125 129 103.2 %
 Number of national programmes developed with WFP support( nutrition, schoool feeding, safety net) national programme
 1 1 100.0 %
 Number of technical assistance activities provided activity 12 9 75.0 %
 SO4: School Feeding( on-site)
 Number of schools assisted by WFP school 182 176 96.7 %
 Gender Indicators
|  Cross-cutting Indicators |  Project End  Target |  Base Value |  Previous  Follow-up |  Latest  Follow-up | 
|  Proportion of women beneficiaries in leadership positions of project management |  |  |  |  | 
|  committees |  |  |  |  | 
 BHUTAN, School Feeding( on-site), Project End Target: 2018.12, Base value: 2015.12, Latest Follow-up: 2016.12
 = 50.00 50.00- 50.00
 Partnership Indicators
 Cross-cutting Indicators Project End Target Latest Follow-up
 Number of partner organizations that provide complementary inputs and services
 BHUTAN, School Feeding( on-site), Project End Target: 2018.12, Latest Follow-up: 2016.12 = 8.00 8.00
 Resource Inputs from Donors
 Bhutan, Kingdom of( BT) 20 Development Project- 200300