Water, Sewage & Effluent Mar Vol 30 No 2 | Page 30

current 15-month time schedule that is now possible using this hybrid technique. The roof was designed by Corestruc, who will also deliver, as well as lift and place the precast elements. At the time of writing, Corestruc was pre-casting the elements of the roof, while the M&D Construction team was forging ahead on site. The roof is supported on pre-cast stubs that are supplied by the sub-contractor and installed on the cast in situ columns. As Venter points out, the contractor is using a full-climbing system from Doka to cast the walls. It is a “walking” system with rails, which has been designed for high productivity. Bear in mind that to complete the four quadrants, formwork has to be placed 16 times and heights will eventually exceed 15m on the last four lifts. As it’s located on top of a koppie, Venter says the site will eventually encounter severe upward winds. He says careful planning is needed to ensure a safe construction site. Interestingly, the wall sits free off the base, with the only connection point being a section of rubber that is placed between the foundation and the wall. He says this was designed by Dunlop and manufactured by Aubert Pipe Systems. Venter says that this also resulted in several technical challenges at the implementation stages, considering that each connection had to be moulded and cured in place, as opposed to being undertaken by conventional welding. Venter says this process takes up to five hours for every connection. All internal pipework started in February. Stepping over M&D Construction was a partner in the MDWK JV on the Pilanesberg North Water Scheme (43km of 1 016mm welded steel pipeline) before taking on this project. When Water Sewage & Effluent visited the project, the joint venture was connecting the pipeline to the reservoir. The pipeline transports water from Vaalkop Dam, the main water source. The pipeline, which was being commissioned at that time, also feeds the mines financing the project. Venter says the reservoir is designed to accommodate two more pump stations to be undertaken in the second phase of the build. It comprises an inlet control 28 Water Sewage & Effluent March/April 2016 chamber with four inlet pipes leading into the reservoir. Another interesting aspect of the build is that the reservoir houses an additional 5Mℓ reservoir inside, acting as a water reserve. M&D Construction’s factory started operating two years ago and it is now manufacturing the first stainless steel pipes to come out of the factory for this project. M&D is also using its team of expert welders, who worked on its pipeline contract at OR Tambo International Airport. This has also kept the works on track. The stainless steel pipes run underneath the reservoir floor and have a five month long lead-time. Another test for the contractor is the VAG valves in the control room that have to be designed and manufactured for the project. Venter says the valve has a traditional casing, but the mechanism controlling the butterfly is extremely spe