PREPPING FOR THE ULTIMATE FOOTBALL PARTY Knowing the NFL Draft would bring even larger crowds into the area, there was a“ big push” to fix the broken link, Rickert said.
The two-phase $ 1 million project began in April 2024 and was completed in early August of the same year, before the start of the 2024-25 Green Bay Packer season and ahead of the 2025 NFL draft, said Trace Hubbard, an Ayres project manager. Ayres did the survey and design work and assisted the Village with some construction oversight and administration.
The project included reconstructing a 27-foot-wide asphalt vehicle travel surface with 24-inch-wide curb and gutter along both sides of the Lombardi Access Road; an 8-foot-wide sidewalk along the south side of the roadway; a 5-foot-wide sidewalk along the north side of Brookwood Drive from Argonne Street to the east of Marlee