familiar with the process before moving forward . “ The City was looking for an alternative solution that would be both cost-effective and constructible ,” Jacobsen said , adding it was also important that scour protection remain buried to replicate a natural stream bed under the bridge .
Despite initial skepticism , the process went smoothly . The riprap installation required careful maneuvering of a concrete pump truck and extendable boom under the bridge to place the grout properly . Ayres Associates oversaw the installation to see that it was achieved according to plan .
Danny Tezak , president of Tezak Heavy Equipment , the project ’ s contractor , said the partially grouted riprap was easier to install than traditional large boulders . “ I think the ( partially grouted riprap ) will have its place ,” he said , such as in confined spaces with tight clearances . “ The concept is very good .”
Tezak is the first contractor in the United States to use this innovative grouting technique , and Pennington praised their willingness to tackle the job . “ Tezak showed a lot of patience and diligence throughout the construction process , resulting in a high-quality project ,” he said .
Ayres Associates adapted the partially grouted riprap method to United States engineering practices as part of ongoing research for the Federal Highway Administration . The process was published in September 2009 as an approved countermeasure for protecting bridge piers against scour .
Construction of the riprap , grade control structure , and bank stabilization measures were completed without affecting the public . The pedestrian trail along the river remained open during construction so the link to the neighboring high school and surrounding areas remained intact , and the bridge remained open to traffic . Construction was sequenced so Sand Creek flows were diverted to one side of the channel while riprap and grout were installed on the other side . This allowed construction to occur in dry conditions to avoid environmental and construction issues commonly associated with placing grout in flowing water .
The improvements will increase public safety by protecting the bridge and surrounding areas in case of flooding . “ This was a total team effort ,” Pennington said . “ The efforts between the City stormwater division , the City bridge department , the batch ( concrete ) plant , Tezak , and Ayres Associates went very well and resulted in an outstanding product enhancing the community ’ s safety .”
If conventional materials and design methods had been used for the riprap design , protection against the 50-year flood would have cost the City approximately $ 140,000 . The partially grouted riprap alternative cost $ 47,000 and provides protection against a 500-year flood .
Ayres Associates exceeded the City ’ s expectations , Jacobsen said , by presenting an innovative approach resulting in an aesthetically pleasing and sustainable solution that did not disrupt traffic during construction .
“ We hired Ayres Associates for its expertise in channel restoration and bridge scour countermeasures , and they did not disappoint ,” Jacobsen said . “ The project was completed on time , and Ayres Associates ’ design saved us considerable money while providing a better solution to a complex problem .”
8│TRENDS
familiar with the process before
moving forward. “The City was
looking for an alternative solution
that would be both cost-effective
and constructible,” Jacobsen said,
adding it was also important that
scour protection remain buried to
replicate a natural stream bed under
the bridge.
Despite initial skepticism, the
process went smoothly. The riprap
installation required careful
maneuvering of a concrete pump
truck and extendable boom under
the bridge to place the grout
properly. Ayres Associates oversaw
the installation to see that it was
achieved according to plan.
Danny Tezak, president of
Tezak Heavy Equipment, the
project’s contractor, said the
partially grouted riprap was easier
to install than traditional large
boulders. “I think the (partially
grouted riprap) will have its place,”
he said, such as in confined spaces
with tight clearances. “The concept
is very good.”
Tezak is the first contractor in
the United States to use this
innovative grouting technique, and
Pennington praised their willingness to tackle the job. “Tezak
showed a lot of patience and diligence throughout the construction
process, resulting in a high-quality
project,” he said.
Ayres Associates adapted the
partially grouted riprap method to
United States engineering practices
as part of ongoing research for the
Federal Highway Administration.
The process was published in
September 2009 as an approved
countermeasure for protecting
bridge piers against scour.
Construction of the riprap,
grade control structure, and bank
stabilization measures were
completed without affecting the
public. The pedestrian trail along
the river remained open during
8│TRENDS
construction so the link to the
neighboring high school and
surrounding areas remained intact,
and the bridge remained open to
traffic. Construction was sequenced
so Sand Creek flows were diverted
to one side of the channel while
riprap and grout were installed on
the other side. This allowed
construction to occur in dry
conditions to avoid environmental
and construction issues commonly
associated with placing grout in
flowing water.
The improvements will
increase public safety by protecting
the bridge and surrounding areas in
case of flooding. “This was a total
team effort,” Pennington said. “The
efforts between the City stormwater
division, the City bridge
department, the batch (concrete)
plant, Tezak, and Ay ɕ́�ͽ���ѕ�)ݕ�Ёٕ��ݕ�������ɕ�ձѕ�������)����х�������ɽ�ՍЁ����������ѡ�)����չ���éͅ���今t($�%�����ٕ�ѥ�������ѕɥ��́���)��ͥ�����ѡ��́����������͕�����)ѡ��ɥ�Ʌ����ͥ�����ɽѕ�ѥ����������)ѡ�����啅ȁ������ݽձ����ٔ�����)ѡ��
��䁅��ɽ�ѕ�䀐��������)Q������ѥ���䁝ɽ�ѕ��ɥ�Ʌ�)��ѕɹ�ѥٔ����Ѐ��ܰ�������)�ɽ٥��́�ɽѕ�ѥ���������Ё�(����啅ȁ������($��ɕ́�ͽ���ѕ́�ፕ�����ѡ�)
���é�����хѥ��̰�)����͕��ͅ���)���ɕ͕�ѥ����������مѥٔ)���ɽ����ɕ�ձѥ��������)���ѡ�ѥ���������ͥ������)���х�������ͽ��ѥ���ѡ�Ё�������)������Ё�Ʌ�������ɥ���������Սѥ���($+�q]����ɕ���ɕ́�ͽ���ѕ�)��ȁ��́�����ѥ͔�����������)ɕ�ѽɅѥ��������ɥ����͍���)��չѕɵ����ɕ̰�����ѡ�䁑������)��ͅ�����г�u)����͕��ͅ�����qQ��)�ɽ���Ё݅́������ѕ�����ѥ�������)�ɕ́�ͽ���ѕϊd���ͥ���ٕͅ����)���ͥ��Ʌ���������ݡ���)�ɽ٥����������ѕȁͽ��ѥ���Ѽ��)���������ɽ������t((