Activity |
Sum of Labor
Hours
|
Debris Hauled
( in cubic yards )
|
Backfill |
12.25 |
0 |
Bridge Deficiency Repair |
108.15 |
6.5 |
Clean ( Vac Truck Pipe Cleanings ) |
206.25 |
32 |
Clean Concrete Channel |
1664.75 |
1843.55 |
Clean Culvert / Bridge |
1774.25 |
2269 |
Clean Earthen Channel |
534.75 |
1053 |
Clean Flume |
586.5 |
224.25 |
Clean Inlet |
482.32 |
188.4 |
Clean / Grade Bar Ditch |
237 |
62 |
Control Vegetation |
450.5 |
168.5 |
Dirt & Mud Removal |
72.5 |
56.6 |
Field Inspection ( No Condition ) |
542.63 |
11 |
Field Verification |
85 |
0 |
Fill Void |
398 |
0 |
Graffiti Clean Up |
102.14 |
0 |
Hydro Excavation |
63.5 |
18 |
Illegal Dumping Response |
54.75 |
102 |
Inlet Decal Install |
52.6 |
0 |
Inlet Inspection |
1071.22 |
0 |
Inspect ( Pipe Inspections All ) |
1034.15 |
0 |
Inspect Channel / Flume |
605.25 |
0 |
Lid Replacement |
15.25 |
0.1 |
Locate Line |
10.5 |
0 |
On-Call |
40.25 |
40.5 |
Remove Debris or Obstacle |
436.75 |
334.5 |
Remove Tree Limbs |
1073.75 |
1109.75 |
Repair Drainage Pipe |
130.25 |
0 |
Repair Drainage Structure |
1312.75 |
110.75 |
Request Line Locate |
3 |
0 |
Saw Cutting |
143.5 |
5 |
Special Events |
10.5 |
0.5 |
Special Projects |
128.5 |
14 |
Storm Inspection |
301.1 |
5.25 |
Trim Trees / Brush |
0.75 |
0 |
Grand Total |
13745.31 |
7655.15 |