TPDES Stormwater Annual Report FY2017 | Page 26

MCM 6 : Construction Site Stormwater Runoff
I . Requirements for Structural and Nonstructural BMPs
Structural and nonstructural BMPs are required by construction site operators through local ordinance that requires operators of construction sites to have an NPDES or TPDES permit to discharge stormwater . Additionally , the ordinance requires these facilities to operate in strict compliance with the requirements of its NPDES or TPDES permit . These permits require operators to utilize appropriate erosion and sediment control BMPs .
The City of Arlington ’ s Community Development and Planning ( CD & P ) Department reviews and accepts construction plats , site plans public improvement plans , and issues demolition , commercial , and residential construction permits . During the reporting period , CD & P reviewed and / or issued the following :
Reviews
Quantity
Plats ( preliminary SWMSP )
108
Site Plans ( SWPPP and SWMSP )
128
Public Improvements
91
Commercial / Residential Demo ( SWPPP )
74
The City requires Stormwater Pollution Prevention Plans ( SWPPPs ) for all building and construction permit applications greater than one acre . The city ’ s permitting process requires BMPs for erosion and sediment controls to protect water quality for all construction disturbances including those less than one acre . During the reporting period , the Environmental Compliance Group received 159 reviewed and approved CD & P SWPPPs as part of the construction application process .
II .
Inspection of Construction Sites and Enforcement Requirements
Environmental Compliance Officers inspect construction sites for compliance with stormwater management requirements and practices and initiate enforcement actions as necessary . Inspections are for large construction sites ( 5 acres or greater land disturbance , or that of any size and located within a common plan of development ) and small construction sites with land disturbances one acre to five acres in size . Sites that disturb less than once acre are also inspected for compliance with the City of Arlington stormwater ordinance . Inspections , investigations , and resulting enforcement actions during the inspection period are itemized below .
Inspection and Enforcement Data ( respectively ):
Residential & Commercial Construction
Quantity
Construction Projects in Progress ( FY17 )
155
Total Initial Inspections ( New construction )
125
Total Site Inspections ( All construction )
1499
Enforcement Action
Quantity
Verbal Warnings
59
Notice of Violation
25
Stop Work Orders
2
Citations
2
Total
88
CITY OF ARLINGTON TPDES STORMWATER ANNUAL REPORT – FY 2017
28 | Page