Timber iQ August - September 2020 // Issue: 50 August - September 2020 | Page 24

LOCAL PROJECT The installation of the ceiling and façade sections. The findings of our test led us back to the drawing board and we redesigned the jointing system of the puzzle pieces. The interlocking joints were redesigned, and blind nut clamp connectors integrated into the connections. We then retested the structure and complied with the standards. When we start the manufacturing process, the primary portal structure took 90 days of cutting (two days per portal), a total of 820 puzzle pieces and 45 days of assembly (one completely laminated portal per day), using approximately 1 920 blind nut fasteners to clamp the portals together. The systems of assembly were also designed for elements to be easily manoeuvred and installed on site. Based on the these ‘small building components’ principles, this allowed us to use vehicles with trailers or a small flatbed truck for transporting. When installation started, it merely came down to the correct sequencing. First the baseplate brackets, our main connections between structures. Secondly, we started erecting pieces into place, again making use of smaller equipment such as telehandlers and cherry pickers to place the portals correctly. The portal had to be erected in two stages, first the short portals and then the larger portals followed, lifted into place and connected with steel brackets. The process of erecting the entire structure took approximately a month to complete. When the primary structure was installed, we moved to the secondary structure. The roof, façade and ceiling structure. The roof structure was constructed using pre-cut and ready to fit on-site Laminated Veneer Lumber (LVL) beams with steel connector brackets. Façade elements being installed parallel to the roof structure installation, all elements contributed to the structural integrity of the building. Once the primary and first stage secondary structures were complete, we proceeded to final testing. The test conducted by the engineers consisted of suspending 950kg from the ridge, and 2 x 650kg from central points in the largest span area. The structure had to support the weight for three hours, without a deflection of more than 45mm. The structure only deflected by 5mm, and subsequently passed. From testing we carried on with further installation of the secondary structure. These ceiling panels and façade structure were designed as clip-on elements to the primary structure (also being manufactured off-site and assembled on-site). The finished product of the Hub – Internal and external views. After the secondary structure was complete, and the building enclosed, we moved to the tertiary structure. This consisted of the fixed furniture and joinery elements in the building, also all manufactured off-site in six weeks and assembled on-site in a week. HOUSING UNITS The design of the elements in the housing units was developed to be pre-manufactured off-site during the construction of the primary concrete and brick structure, transported to site when the units were completed and installed on-site within a matter of hours. Elements that could be handled by hand, positioned in place and fixed. 22 AUGUST / SEPTEMBER 2020 // www.timberiq.co.za