Timber iQ April - May 2019 // Issue: 43 | Page 24

PROJECTS The team worked hard to make the project a success despite encountering many challenges. The Lanzerac Hotel is a heritage site. had to be reduced smaller sizes (200mm x 300mm) and to achieve this, more than three sections of lumber was used. All components were joined together by mortice and tenon as well as SPAX screws supplied by Faitsch Products. Special Festool tools supplied by Vermont Sales were used on the various joints. Rooftek Trusses also took responsibility for erecting and installing the structure. Because the building more than a century old, some of the walls were not in a good shape. As such, specialist brackets were made to help with the loads involved. There is no doubt that the project was challenging, however the team managed to work well together to have it complete in about five weeks. Commenting on the project, Kalahari Bruwer, the roofing contractor says, “As some have seen the final result, I would like to thank all involved for giving Rooftek Trusses the opportunity to be part of a project of this magnitude and at such a special place as the Lanzerac Hotel.” QUICK FACTS • 70m plus of spruce • ± 10m 3 of SAP • Weight per truss: 650kg plus • ± 1.3m 3 of timber per truss • Completion time was roughly five weeks 3 22 APRIL / MAY 2019 // Continued from page 20 The roof of the Lanzerac Hotel after construction following a devastating fire. PROJECT TEAM Project manager Con van der Colf Engineer Mark Hutcheson Contractor Ben Pretorius / Stabil8id Roofing contractor Rooftek Trusses Kalahari Bruwer www.timberiq.co.za