The Ingenieur Vol 57 January-March 2014 The Ingenieur Vol 57 January-March 2014 | Página 15

Figure 5 – Remedial Works at Lepoh Fault Figure 6 – Face Collapse at TBM 2 Figure 7 - Rock and Ingress Water Temp Figure 8 - Temperature of Water, Air and Rock The cause of the high temperature is still under investigation by local universities. Measurements of rock and water temperature were taken at regular intervals. The data obtained was analysed for health and safety reasons of the workers working in the tunnel. Figure 9 shows the measurements recorded in the tunnel. To overcome the low productivity of the workers and hazardous working environment, additional chillers and air conditioning units were installed to reduce the ambient temperature inside the tunnel. Special vests were used by the workers during working. As a result the ambient temperature was reduced to desirable limits. Figure 10 shows the results of the ambient temperature after additional chillers were installed to overcome the high temperature. High Water Ingress Groundwater ingress caused problems in the TBM1 and TBM-2 and these were generally dealt with by providing adequate dewatering measures. The amount of the ingress water during tunnel excavation was estimated as relatively small based on the results of series of geological investigations and the ground water analysis. The counter measures were mainly focused on ensuring the tunnel face was stabilised during excavation. However, it imperative to be prepared for the worst case scenario of a large amount of water inflowing into tunnel, caused by unexpected poor ground conditions, or the collapse of the work face under a river. With this in mind, several countermeasures were taken both inside and outside the tunnel. A dewatering system with a capacity of 10 tons per minute was installed at the Junction of Adit1 tunnel and the Main tunnel at the beginning of the project. However, in order to treat a larger amount of unexpected water inflow up to 20m3/ min a stop-log utility was prepared at the Junction to secure enough time for evacuation of the main machineries and for installation of additional dewatering equipment. During the excavation at TBM 1, the ingress water the total quantity exceeded 16m3/min. A similarly problem was experienced at TBM 2. As a result the working area was flooded. The high water ingress at both TBM’s made it impossible for the excavation work to continue for safety reasons 13