The Ingenieur Vol 57 January-March 2014 The Ingenieur Vol 57 January-March 2014 | Page 12

COVER FEATURE INGENIEUR Challenges in the Construction of the Pahang-Selangor Raw Water Transfer Tunnel By Dr Zullkefle Nordin Project Director, Pahang Selangor Raw Water Transfer, Ministry of Energy, Green Technology and Water The state of Selangor especially the Klang Valley, Federal Territory of Kuala Lumpur and Putrajaya have experienced rapid development over the years. The statistics for water demand for these locations shows there was increase from 2440 million litres per day (MLD) in 1998 to 3809 MLD in 2008. This trend of increasing water demand at 3.3% per annum is expected to continue in the foreseeable future. The water demand for 2025 is projected to be about 6242 MLD. To meet the increasing water demand, the Federal Government has decided to look for alternative water resources beyond Selangor. The development of water resources requires long distance transfer and hence becomes more expensive as most of the resources close to the demand centres have been fully developed. The Pahang-Selangor Raw Water Transfer Project (PSRWT) was identified as the most viable option to meet water demand for Selangor and Kuala Lumpur’s in the future. Introduction This project aims to relieve shortfalls in water supply for daily life and industries of Kuala Lumpur and Selangor State in the future (supplying approximately 1890 MLD) of raw water from Pahang State to Kuala Lumpur and the surrounding areas. The project consists of four packages; 1. Raw Water Transfer Tunnel, 2. Kelau Dam, 3. Pump House and Intake Works, and 4. Raw Water Twin Pipelines. Figure 1 shows the overall view of the project. The consultant engineer was appointed in 2005 for the design work. This project was financed by the Government of Japan (GOJ) through the Japan International Co-operation Agency (JICA) and the Government of Malaysia (GOM). The overall cost of the project is budgeted to be RM3.93 billion of which GOJ will finance 75% of the construction costs. The procurement procedure used is the 6 10 VOL 57 JANUARY-MARCH 2014 VOL 55 JUNE 2013 International Competitive Bidding procedure as requested by JICA. The conditions of contract used is the Federation Internationale Des IngenieursConseils 1987 (FIDIC 1987). The construction works began in June 2009 and all the works (all the four packages) will be completed by the May 30, 2014. Figure 1 shows the progress of each individual package. As at the end of November 2013 the overall progress of PSRWT was 90.3%. In this article, the author will concentrate only on the challenges encountered during the construction of the raw water transfer tunnel. The Raw Water Transfer Tunnel The tunnel is the seventh longest water tunnel in the world and the longest in the Asian region. It is 44.6km long with 5.2m diameter. It includes three sections of 34.6km each excavated by Tunnel Boring Machines (TBM), four sections each with a length of 9.1km excavated by conventional tunnelling methods (New Austrian Tunnelling