Work begins on Glen Bowen Station gully ork has started at Glen W Bowen Station, LDC’s second large-scale gully remediation site. Machinery was mobilised in November, and earthworks are expected to be completed by mid- December. Cultural heritage field survey and assessment cultural heritage survey and A impact assessment was completed on Glen Bowen in consultation with the Birriah People to address NQ Dry Tropics’ statutory obligations and cultural heritage duty of care under the Queensland Aboriginal Cultural Heritage Act 2003 (ACHA). Mt Wickham Phase Two works complete ully remediation G phase two at Mt Wickham has been completed. The work consisted of a series of rock chutes in both the main gully and the side gullies. LANDHOLDERS Driving Change is a Burdekin Major Integrated Project funded by the Queensland Government through the Queensland Reef Water Quality Program. Grit, Issue 17, December, 2019 | P25