Stadler says the construction cost is valued at R330-million. The civils work alone is priced at R3-million and lateral support at R4-million.“ During the bulk earthworks, 20 000m 3 of material was removed, which was all completed during the month of June, of which about 8 000m 3 was rock blasting.” Blasting had to be done particularly carefully, he says,“ with low-impact explosives and monitoring” because a Gautrain tunnel runs 72m beneath the site and the Gautrain Management Agency consequently has a servitude over the site precisely where the rock is located.
A specialist blasting company performed the blasting under the auspices of engineers, and with monitors located strategically at all points of the site to measure the impact.
Van Jaarsveld adds that the size of the site is approximately 3 800m 2 at a cost of R3 000m 2 for a total cost of R71-million. The site will be fully developed with“ a bit of a driveway”. The development consists of: »»
152 brand new apartments.
Sizes range from 22m ² studio apartments to 235m ² threebedroom apartments and fourbedroom penthouse apartments ranging from 482m ² to 651m ².
»»
Brand new sectional title A-grade office units. Sizes range from 69m ² to entire floors where the footplate is 1 950m ². The total office component is 4 440m ².
»»
An upmarket ground floor retail area.
»»
First-class 24 / 7 manned security with smart automated access control and patrolling guards.
»»
Liberal parking provisions for offices with a ratio of five bays per 100m ².
»»
Exclusive upmarket entertainment area / executive rest centre for corporate functions, Friday drinks, or wellness activities.
»» A wellness centre.
»» High-speed fibre Internet.
»»
Joggers’ showers, change rooms, and bicycle racks to encourage occupants to embrace a more
active approach to work-life.
»»
A generous number of storerooms.
»»
Five high-speed lifts provide rapid vertical transportation.
»»
Automatic standby power and backup water supply.
»»
Pet friendly.
Approximately 30 000m 3 of concrete and brick spoil was crushed on site and that material transported to a quarry in Crown Mines.