The Civil Engineering Contractor May 2019 | Page 23

ON SITE: PROJECT 2 T he P105-million project was initially earmarked for commencement in 2014 (and had first been mooted as early as 2009) under the Botswana Department of Roads, but was taken over by SPEDU in April 2017 for facilitation. Platjan is located in the Bobirwa sub-district, where there are border posts on both sides of the Limpopo River that constitute points of entry between Botswana and South Africa. The determining design criteria of the bridge was to design at sufficient level above the 15-year flood line. The bridge is therefore cambered and raised in relation to approach roads. The in situ bridge deck spans onto prestressed concrete bridge beams 800mm deep, spanning 15.5m continuously over 1m thick by 9m-high tapered concrete piers. www.civilsonline.co.za These are typically founded on 1.2m thick × 9m × 4.5m-wide concrete bases with 8No. × 5m deep, 32mm diameter high-yield anchor dowels on the upstream side and 4No. × 3m-deep base anchor dowels on the downstream side of the pier bases. The final finish over the bridge will be a 60mm layer of asphalt with the approach roads having concrete paving. Two agricultural culverts, each 5m wide by 2.5m high, are provided at chainages +0.180 and +0.420, respectively. Site project manager with Estate Construction, Julius Katzke, explains the commercial basis for the project: “The Platjan border post is currently not a commercial border. The nearest commercial border is heavily backed up with trucks waiting hours to cross, and the strategic intent of this development is therefore to turn Platjan into a fully fledged commercial border post to ease that logjam and simultaneously stimulate the local economy by providing improved access for small towns and big farming enterprises that are located within a 35km radius. Increased through- traffic will also create opportunities for local hospitality businesses in and around the border post.” There is 40km of gravel road leading to the border post on the South African side, and more on the Botswana side. These would have to be paved. The current bridge is regularly affected by seasonal flooding, making it impassable for both vehicles and pedestrians. The most affected are farmers in both countries, as they experience a great inconvenience in crossing to either side to sell their produce. The business and farming communities in the Tuli Block area have engaged in business partnerships with South African-based entrepreneurs on the other side of the border. The Platjan Bridge upgrade is part of a bilateral covenant in which the South African government committed to construct a bridge across the Notwane River in Ramotswa. Both bridges are located at international border posts and are meant to ease travel between the two countries. Scope of work The bridge is of concrete and a hybrid construction, its span being 155m with 10 equal spans. The overall bridge width is 12.7m. The single carriageway has two 3.7m traffic lanes — one in each direction — with a 2m-wide pedestrian walkway on either side of the traffic lanes. The new bridge dwarfs the existing bridge level alongside, being 7.5m higher. The current means of crossing the river is through a single lane causeway or low-level culvert with concrete pipes along the 100m length of river width. Quantities of material include: • About 13 000m 3 of rock fill. • About 3 500m 3 of gravel material. • A total of 220 rock dowels will be drilled into sound rock. • A total of 54t of reinforcing steel will be used for in situ culverts construction. • A total of 400m 3 of 40N concrete will be used for in situ culvert works. •  A total of 3 200m 3 of 40N concrete will be used for the main bridge works. • A total of 210 prestressed T bridge beams, each 15.3m long, will be transported to site and erected. • 120t of steel in the deck • 2 200m 3 of concrete crunched. At end-January, the bridge was 72% complete, and was consequently somewhat more advanced at the time of the March site visit by Civil Engineering Contractor, with all the foundation concrete work done by that time, barring the deck slab and approach roads. The contractor commenced work in early January 2018 and the project is set for completion by end-June. Katzke says the project, as a Botswana project, had to procure from local Botswana ‘citizen companies’. One exception was the precast concrete beams, as these were not locally manufactured to the appropriate quality, he says. Jaco CEC May 2019 | 21