The Civil Engineering Contractor March 2019 | Page 26

ON SITE previous project, so we changed the design to position them differently — and now it works perfectly. “We do the same thing over and over, so our intellectual capital is constantly developing through repetition, enabling us to learn and invest in our technology.” The company also does stadiums, bridge beams, and parapets, in addition to structures, namely retail, industrial, and commercial buildings, and bespoke projects. Where the possibility exists for things to go wrong, says De Jager, is in the accuracy of the factory casting. “Ten panels are manufactured at a time. Each panel has its own drawing and its own quality process and quality documentation recording pre- inspections, post-inspections, and concrete strength (70–80Mpa). The way we achieve these accuracies is by having control of the whole process, and it was for this reason that we opened our own engineering shop, which enabled us to manufacture and cast-in components that we intended while designing the shutters ourselves. Without that total control of the process, something somewhere would likely be missed and then the total installation would not work. It is this total control that speeds up the process.” While the walls were still being installed, the centrepiece of the roof was constructed and the first panels for the perimeter of the roof delivered. These have a 10.8m span and are 250mm thick. The panels are installed without the use of props — except the first — which would encumber the space other workers need. When the first panel of the wall is set with external props, each subsequent panel is set against the previous one. “An important aspect of the design is an understanding of how the different trades all work, so our process does not obstruct any of them,” says Meyer van Rooyen, Corestruc’s project manager. A concrete pump on site is required to be highly variable, as the nature of the project means that 24 | CEC March 2019 Willie de Jager, managing director of Corestruc (left), with Rudi Bezuidenhout of Mbako Projects & Trading. small quantities of concrete are often required (as little as 5m 3 /hour), increasing sometimes to 30m 3 /hour. One particular problem of the site, which slowed the project, was the shortage of aggregate, says Kunaka, as there were no suitable quarries or borrow pits in the area. “We initially had access to suitable material from a local borrow pit near Kwaggafontein, but the quality subsequently deteriorated during construction. We had already finished with the earthworks, and because conditions were wet, we initially could not identify changes in the material. But once we finished with compactions and it was dry, the concrete started to crack and that is when we realised the material was unsuitable. We had to rip out the whole floor platform and bring in new material. We required G6, but the borrow pit had downgraded to G7 and G8. In particular, the clay content was too high. We ended up using commercial material after testing all the borrow pits around here but couldn’t get the proper material.” The ‘mother’ ship The view from Mathysenloop is hilly and scenic, with numerous reservoirs visible on surrounding hills — some part of the broader programme, though not of this particular project, the reservoir at the centre of which is the ‘mother’ that feeds them by pumps. Currently, many of the existing reservoirs are fed by borehole water, which is insufficient. Bezuidenhout explains some of the surrounding work: “A 13km pipeline stretches from Bundu to Boekenhouthoek and on to Mathysenloop, where there is a chamber which has an outlet pipe into the reservoir for storage.” The trench for the long pipeline is dug by excavator down to the rock foundation, at which level drilling and blasting is used to get the level down a further 1.5m to 1.8m. “It must be placed at a certain depth because the pressure on this pipe is enormous,” says Bezuidenhout. He explains that the major challenge of the project is the rural nature of the location, which is typical and expected — and there is none of the politically motivated stoppages that affect so many other projects in South Africa. Bezuidenhout explains that local communities have been well involved in the work and supportive, with 30% of the contract work having been allocated to community contractors. “They bid for the work and we selected the best ones. They were involved with digging the trenches, the drilling, and the blasting and they were good.” nn www.civilsonline.co.za