The Civil Engineering Contractor June 2019 | Page 23

AJ King, site manager for Shotcrete Africa SCP and supervisor Alphious Mahlabela. the structure while improving its appearance. The structure rises up towards the building entrance and narrows down to a diminishing point – indicating the way to the door almost like a target. That was the biggest challenge from a design point of view. Once I had decided on that design, I had to look at what I could take away – one usually has heavy buttresses on an arch, but we were able to do away with this due to the capabilities of the concrete and the expertise of the engineers we were working with,” says Breytenbach. “We wanted to open up the western side of the structure and have sufficient natural light, and we were lucky in that protection from the elements was afforded by the existing building. We used polycarbonate as a roofing material, because it doesn’t transfer a lot of heat, clad over ribs tucking into the structure on the sides which turned three-dimensionally.” As you approach the building the portico opens up in a well-lit manner, closing in as the entrance is neared, tilting up slightly. Two large pillars and the gutters act as the keystone to the structure. There are long spans of unsupported cantilevered concrete between the pillars, “and that’s a homage to the material we’re working with and what it is capable of,” explains Breytenbach. www.civilsonline.co.za Scope of work “I believe this is one of the only structures where every element of rebar has its own bar-mark – every single piece is individual, because everything is either diminishing or increasing in size and the whole structure is moving in three directions. It’s not like a normal column.” The steel design was done by engineers SCIP (Francois Deysel and Jacques le Roux). Peri was responsible for the formwork, lay out and assembly. Each was cut by laser into 200mm sections so that Peri could get the stop ends correct, because each one turns. “We didn’t want to place the covering material on top but below in order to create a draught through it. It was impossible to cast it as a sleeve in situ, and that is where Shotcrete came in when we looked at how to practically build it,” says Breytenbach. With sufficient admixtures such as Penetron added to the concrete, a slump of just 55 to 65 was achieved. The columns are 800mm deep and 2.4m wide, and a whole column could be erected in a single day without shuttering at the back. “It is quite amazing,” enthuses Breytenbach. With lateral support, the result was that the structure did not have a weight of concrete pushing down. From Peri, Callie Middel (estimator), Shane Treherne (sales engineer) and Jacques van der Walt ON SITE Architect Pieter Breytenbach, of Deter Architects & Designers. were responsible for the project. Middel explains that Peri was responsible for the design work for the formwork and shoring, which was done by Jacques van der Walt, senior formwork designer at Peri. “All formwork elements for the soffits were pre-fabricated by Peri off-site to be delivered for assembly on site. This was however not possible in the case of the formwork and many items were attended to by AJ King (site manager for Shotcrete Africa SCP) on site. This project was unique to say the least as well as challenging in terms of formwork, reinforcing and the shotcrete operation. The solution to constructing the canopy had to be found in a close collaboration of the trades involved, architect Pieter Breytenbach and his team, the team at Peri, the rebar team and the team at Shotcrete,” says Middel. “The structure is asymmetric so section and formwork design work had to be done in 3D taking existing structures into account. From a formwork point of view, this project was highly unusual and many contractors took the decision not to get involved. The placement of concrete is only possible by the wet-shotcrete method,” says Middel. Shotcrete Africa SCP, with assistance from Peri, installed all the formwork. The construction method started with the installation of a designed network of props and scaffolding to CEC June 2019 | 21