The Civil Engineering Contractor June 2018 | Page 17

ON SITE The first of 96 piles being drilled into the soft earth. The piles are various diameters, ranging from 500mm to 1.2m. in the mix ensures that when the mix leaves the nozzle and impacts with the wall, it stiffens, or firms within about 20 minutes,” he adds. Alford says that initially, the mix contained stone, measuring 9–14mm, but that changed. “While the finish was okay, we removed the stone and increased the sand content, resulting in a much nicer finish, with the same strength,” he explains. Challenges All three professionals agree that while the weather creates a challenge, it is the logistics that is the greatest to overcome. The proximity to busy roads within a built-up area poses multiple challenges, as there is the noise component to deal with, compounded by limited access to site, creating little to no laydown area. A ready-mix concrete truck gingerly negotiates its way down the ramp after the extensive rains. “We are at the early stage of the design development, so we have brought Solid Green on board to advise us on how best to optimise green building principles.” Dev Devan, 3D Projects Alford says: “The weather is a challenge. However, with projects of this size, the main issue is normally logistics, because the earthworks company needs to bring multiple trucks on site, while we want concrete on site and need a place to store our steel and equipment. If tight sites like this are not planned properly, it can turn into a mess. Even the on-site offices had to be removed once the wall had reached its optimum height.” He continues: “In addition, there is a substation on the site, which created a problem. Normally on sites like this, that area would be kept open, enabling us to erect a site office or create a laydown storage area. But on this site, we have gone down so deep that we needed to take the stuff off the top, namely, the site offices. “Other than that, we are going well, and we are ahead of schedule. The earth is soft, which makes it easier for us to drill; the trim is easier for the Shotcrete; and the earthworks are easier as there is no rock.” “The main concern has been around the extensive rain that has fallen over a short period of time, waterlogging parts of the site, bogging trucks down in the mud,” Moonsamy adds. Harrogate has 10 trucks a day running backwards and forwards from the tip site in Midrand. Devan concurs and adds that the tight programme also poses a challenge, exacerbated by the vast amount of CEC June 2018 - 15