The Civil Engineering Contractor July 2019 | Page 24

Sam Mhlaba, CEO of Montrose City Mega Development. Project launch. Bank of Southern Africa (also a partner in the SPV) and have reached agreement on a plan of action which will be implemented during the next two years as phase 2 materialises, to provide sufficient electricity.” For instance, there are plans for two adjacent solar plants covering 30ha each over a 20-year period, which may ultimately provide power. Further ‘greening’ of the community will stem from plans to recycle grey water within the community for industrial purposes rather than returning used water to the municipal infrastructure. These will become part of phase 2. Mhlaba says that during the construction peak, between one and two million cubic metres of concrete were being poured each week. The scale of the work means a number of different suppliers are involved, including AfriSam, WG Wearne and Senzobex, while cement was also provided by PPC, and third-party suppliers such as Cashbuild and Bricks for Africa. The current state of the project: • The installation of services was started, which includes water reticulation, sanitation/sewer, roads and storm water. • In September 2018 the installation of services on Phase 1C was started. • In October 2018 the construction of top structure commenced units which include military veterans units, and BNG RDP units. 22 | CEC July 2019 ON SITE • E  stimated completion of services being installed on Phase 1A is June 2019. •  Estimated completion of the services being installed on Phase 1C is July 2019. • Estimated completion of the top structures is on June 2019. • In June pipe jacking will commence for the following across or underneath the railway line: storm water, electricity, sewer/sanitation. • Developers are currently busy with the town planning services for Phase 2, which will yield 8 190 units known as Montrose Ext 1. • The duration is six years, which will overlap with phase 1. • Developers are in talks with Prasa and Transnet on the development of a passenger train station similar to Johannesburg Park Passenger Station. Materials used to date: • Cement stock bricks – 10 million bricks • Maxi bricks – 1.5 million bricks • Clay bricks – 1.2 million bricks •  Concrete steel reinforcement 600t • Concrete – 10 000m 3 • Cement – 18 000 bags of cement 32.5kg • Aggregates – 15 000m 3 building sand and 7 500m 3 plaster sand • Roads and storm water – Asphalt roads 17.1km • Sanitation/sewerage – 17.1km • Water reticulation – 19.3km Challenges There was a lot of rock on site, requiring both packing by jackhammer and excavator, and blasting. This delayed the start of civils work by some time, says Mhlaba. There was considerable community excitement and expectation at the commencement of works, says Mhlaba, but not unexpected given the high levels of poverty and unemployment in the area. This was resolved through communication and education: “People realised this was a long-term project and they should not be impatient to see some benefits, as we will get to everyone.” Bulk infrastructure was an initial problem but was escalated and resolved with the municipal service providers to prevent hindrance to the development, especially the larger phase 2. In a development as complex as this one, the developer could not afford to sit back and rely on the pace of government action, as momentum was vital. Mhlaba says SCM took the initiative in bringing together all the parties – Transnet, Prasa, Department of Education, Human Settlements, to ensure all the legs moved in a synchronised fashion. “It was a journey that began in 2015 until we broke ground in November 2017. As the land was a farm, it had to be converted to a township for planning purposes. We acted as enabler of all the professionals, and the myriad processes: EIA, www.civilsonline.co.za