The Civil Engineering Contractor July 2019 | Page 18

ON SITE A panoramic view of the site, overlooked at SABC’s Auckland Park campus. the job from sitting in an office. The guys I have who ‘get out there’ are able to operate all our equipment.” Overview of challenges project Both Khune-Con and Lapalaka are family-owned businesses (Wick works with his father Erhardt, a qualified quantity surveyor who does the QS component of the project). They frequently do JVs on such projects in the area, as well as in Pretoria. They are consequently well known to each other with high levels of trust. Burger says his company prefers to work within trusted relationships and seldom tenders for work. As the main contractor, Khune-Con was responsible for the demolition, civils work and construction to key handover, explains Burger, as well as external work on roads and pavements. The full civils work used 650m 3 of concrete for the ground beams and 27.5t of steel, and 2 500m 3 of soil replacement was removed at a cost of R150/m 3 . The full quantities had not as yet been quantified for the entire structure. “First we build all the retaining walls around the site to create the platform by doing 150mm layer 16 | CEC July 2019 compactions up to 93% modified Aashto specification. From there we pile to the exact top of pile height, from where we dig our ground beams on top of the piles and from there we build the structure. “The main challenge with a project of this nature is time. Developers need to be complete on a previous project and ready-to-go before they get the go-ahead on a new one. This is because students sign in mid-February to end-February, and the project has to be complete by then. We therefore start demolitions on the next project in March, which means we have eight months in total to execute. In fact, on the previous project we had only six and a half months, and it was a bigger project than this. If we don’t make it in time … you can’t ask students to move in during July. When you miss a deadline, you miss a year. In terms of penalties, if we’re late a week it can cost the developer a year, so how do you cost that?” It can potentially liquidate a developer that’s not sufficiently financially strong. That explains the need for trusted relationships. “On some projects I run two nine- hour shifts for months on end to meet the deadline — but it won’t be necessary on this one. This requires us to have all material delivered on time and it consequently can’t be dependent on availability of cash flow. When we’re in full production we get about six truck-loads of bricks a day, and 12 truck-loads of dry- mortar mixes because this can’t be mixed by hand on site. The latter can be stored in silos where we add water to get, say, 10MP or such strength as is required. It’s a class A mortar mix we use. We use Echo precast slabs, where we can, for the floors and ceilings, but some areas require massive spans which have to be done in situ,” says Burger. Early delivery in itself creates a challenge with logistics because of the built-up nature of the area: bricks are palletised, shrink wrapped and stacked up, with a 4X4 all-terrain forklift telehandler capable of lifting pallets as high as five floors. Double handling of the dry mortar was avoided by mixing it directly on the slab, where water was added. “The silos are consequently just a back-up plan, and to mitigate against potential delays in delivery — after all, we cannot afford to stand idle.” An administrative challenge at the moment is lack of continuity from local authorities. Burger explains that because of a backlog in building www.civilsonline.co.za