The Civil Engineering Contractor July 2019 | Page 12
INFRA AFRICA
The project is taking place in a pristine part of the Lesotho Highlands.
LHWP II diversion tunnels construction underway
The Lesotho Highlands Development Authority (LHDA) has
awarded the R517-million contract for the construction of
the Polihali diversion tunnels to SCLC Polihali Diversion
Tunnel Joint Venture, marking another significant step in the
implementation of Phase II of the Lesotho Highlands Water
Project (LHWP).
The contractor has been on site since April with the works
expected to be completed in approximately 18 months.
The project cost is estimated at R517-million. The SCLC
Polihali Diversion Tunnel JV combines international, South
African and Lesotho expertise: Salini Impregilo S.p.A
(South African branch), Cooperativa Muratori Cementistri
CMC di Ravenna (South African branch), LSP Construction
(Lesotho) and CMI Infrastructure (South Africa).
“The diversion tunnels are essential to facilitate the
construction of the Polihali Dam. Their construction
is an important element of the advance infrastructure
works which started towards the end of 2018 with the
awarding of the contracts for the Polihali North East Access
road and the civils work at Katse and Mokhotlong. The
advance infrastructure will largely be completed prior to
commencement of construction of the Polihali dam and the
Polihali to Katse water transfer tunnel,” says Tente Tente, the
LHDA’s Divisional Manager, Phase II.
Diversion tunnels divert water away from the natural river
bed to create a dry foundation and work area needed for
the construction of a dam. Their construction usually goes
along with the building of cofferdams, one upstream and one
10 | CEC July 2019
downstream of the proposed dam, which together allow the
river flow to bypass the dam foundation area.
In the case of the Polihali Dam, two diversion tunnels
will be constructed to divert the waters of the Senqu River.
Building two tunnels will increase the capacity to carry
floods and will provide flexibility to work in one tunnel
while the river flows in the other one.
The tunnels, one 7m in diameter and almost a kilometre
in length, and the second, 9m in diameter and also almost
a kilometre long, run parallel to each other from the intake
point to the outlet downstream of the dam. The tunnels
will be excavated by drill and blast method, and will be
supported by rockbolts and shotcrete as required.
The Metsi a Senqu-Khubelu Consultants Joint Venture
(MSKC) which also includes a number of South African and
Lesotho-based firms such as Aurecon (SA), Knight Piesold
(SA), Hatch Goba (SA), SMEC (SA) and FM Associates
(Lesotho), has designed the diversion tunnels and will also
supervise the construction work.
The LHWP delivers water to the Gauteng region of South
Africa and utilises the water delivery system to generate
hydro-electricity for Lesotho. Phase II will increase the current
supply rate of 780 million m 3 /year incrementally to more than
1 270 million m 3 /year. At the same time, it will increase the
quantity of electricity generated in Lesotho and is a further step
in the process of securing an independent electricity source to
meet Lesotho’s domestic requirements. nn
www.civilsonline.co.za