The Civil Engineering Contractor July 2019 | Page 10

CONTRACTORS ON SITE An innovative design-and-build solution for the USD220-million Japoma Sports Complex in Douala, Cameroon, has seen integrated infrastructure delivery company AECOM slash two years off the traditional timeframe for such a mammoth project. The Japoma Sports Complex consists of a 50 000-seat multi-sport stadium, an aquatics centre with an Olympic-sized pool, a 50 000-seat multi-sport hall, outdoor training facilities, and transport hubs and site infrastructure. Ground was broken in 2017, with the formal opening anticipated in June. AECOM’s scope of work encompassed a comprehensive scheme design for all engineering and architectural services, including master planning, and a design guardianship role as the project moved into production on-site. From a blank slate with no masterplan in place to a fully operational stadium normally takes three to four years. However, the original timeframe was even tighter, with practical completion aimed for by October 2018. Adding to the complexity was the fact that the bulk of the labour, materials, and elements had to be imported from main contractor Yenigün’s home country of Turkey. Thus, shipping delivery lead times required precise planning and logistics. Constraints faced in this regard meant that many of the early trades were eventually carried out on-site. A batch plant produced readymix concrete for all of the precast elements to be cast on-site which, in turn, required a massive production yard for storage and handling. nn 8 | CEC July 2019 Concor builds safari lodge at Skukuza AECOM cuts stadium design-and- build to a record two years at Japoma The western terrace overlooking the function area. Concor Buildings recently completed a new three-star safari lodge at Skukuza camp. Planned and constructed as a ‘green’ building, Skukuza Safari Lodge boasts 128 units, including 87 standard rooms, 20 family rooms and 13 universal rooms with easy access for wheelchairs. Work began in February 2017, with the team leaving site at the end of March 2019. According to Concor Buildings’ site agent, Christopher Martin, the environmental focus was taken on board by the team and applied with commitment in various ways. In line with green building requirements, the two-level structure does not protrude above tree level, minimising its visual impact. Architectural timber is a prominent feature of the lodge, with laminate saligna beams used for long-span trusses. Thatched roofing and grass ceilings add to the natural ambience, along with design elements from local cultures. While making every effort to be non-intrusive, the lodge is a substantial construction with 5 200m 2 of decking. More than 3 600m 3 of concrete has been poured over 150t of reinforced bar, and 1.8 million bricks have been laid. The coverage of roof thatching measures over 3 600m 2 , while 5 000m 2 of sheeting has been used. In recognition of the authentically wild surroundings of the lodge, an important use of the concrete was in the bases of the game fence. The fence has been built all around the lodge, with substantial bases measuring in size from 1.5m x 1.5m to 1m x 1m. The site itself presented a few challenges, with much of the infrastructure dating back many decades and not all precisely recorded in terms of location. Further investigation through radar technology and even geographic positioning systems (GPS) was sometimes necessary to identify underground services. Most services such as fresh water, grey water and sewage had to be re-routed in line with the needs of the new structures. An ongoing challenge was the distance between the site and the towns from which products and services were sourced. Being two hours from Nelspruit, for instance, added to the logistical burden and lengthened lead times, especially considering the road speed restrictions within the Kruger Park. nn www.civilsonline.co.za