The Civil Engineering Contractor January 2018 | Page 19

ON SITE “This first phase was crucial, as these walls supported those buildings and any mistake in calculation would have been disastrous,” Alves says. In the first phase of the process, Franki supported the walls with 249 no. four-strand anchors and, simultaneously, 82 no. soldier piles were installed on the northern and eastern faces, which included Maud Street and Rivonia Road respectively. This intricate operation took from 1 December 2014 to the middle of April 2015 and, shortly before the end of this phase, permission was granted to proceed with phase 2, which was to demolish the existing four-basement parking garage, excavate according to the new plans and then laterally support the remainder of the site. The three main disciplines – geotechnical, earthworks and demolition – worked concurrently on a confined site, which presented enormous challenges, overcome fortunately, by close collaboration and excellent cooperation between the various contractors. Alves comments, “From the client, Eris Properties, through to the project managers SIP, AECOM quantity surveyors, Aurecon engineers, Boogertman and Partners architects through to the contracting team of Franki, earthworks specialists Zero Azania, Phoenecian Demolition, Pro-Frag Drilling and Blasting and Diamond Cutting and Coring Company, there was cooperation and understanding that made the success of this job possible.” A task that was both i mportant and intricate, happening out of sight, was the separation of the basement from the existing structures of the Balalaika and Protea Hotels. Alves explains, “This was achieved through precision cutting and sawing by the Diamond Cutting and Coring team under the supervision of Aurecon who ensured that the cuts were made in exactly the correct positions. There was absolutely no extraneous damage in this critical operation.” Also happening around the site were relatively minor civils jobs that involved the surrounding buildings. Although they were minor, they were nevertheless critical in that they made it possible for neighbouring businesses to continue their day-to-day activities uninterrupted. These included: the regrading of the Holiday Inn Hotel entrance; the creation of emergency walkways for safe passage to and from all the surrounding hotels; erection of all the hoarding around the site and making safe the common areas with the surrounding buildings; and the relocation of storm water and sewerage pipes. In addition to all the ancillary civils work, Franki had to control the noise “With a project like this you allow for a substantial contingency. We managed it with our contingency.” James Reid, AECOM. level and the dust on site. “This was exacerbated by very hard granitic rock that we encountered which required drilling and blasting. One can imagine just how controlled this operation had to be to do it not only safely, but also as quietly as possible and with as little dust as possible. Once again, the teamwork was exemplary,” Alves says. Additional considerations Time is always the task-master on jobs of this magnitude and this project was no different. The location of the site necessitated that the work day be strictly limited to between 07:00 and 18:00, while the ‘unbelievable’ volume of ground water present on the site, created time pressure resulting in the constant collapsing of the soldier-piled side walls, necessitating temporary casing of all the piles. In addition, underground there was a ‘maze’ of services which had to be avoided or moved about. This was compounded by the fact that there was almost no information about the services, which slowed processes down significantly. In fact, an anchor did strike an underground sewerage pipe in a position that made it very difficult to repair. Also, a challenge as far as time was concerned, was the 3 000m³ of contaminated soil, detected by a strong petrol odour. “We believe this may have been caused by an old petrol station on the site which had leaked petrol over many years,” Alves says. “We got Envirowaste to isolate the contaminated area and of course it had to be excavated with great care. This unforeseen challenge took its toll on time and delayed the programme somewhat along the Maude Street face.” As luck would have it, the contaminated area was located exactly where the first handover section was. The building contractor was scheduled to take over the Phase 1 of the site at the end of October 2015. However, the full extent of the contaminated area could not be determined at the time. In addition, the contaminated soil was up against the lateral support face, limiting the progress of this critical-path operation. Nevertheless, with some creative lateral thinking Franki made up the lost time and the building contractor was able to establish by the required date and the lateral support of the demolished basement went ahead as planned. Alves emphasises this was technically the most challenging project he has ever been involved in. “This was truly an incredible, unforgettable contract, which, more than anything, displayed the power of teamwork,” he attests. Construction status Reid assures that the project is ‘pretty much on time with the construction’, while procurement, on the other hand, ‘has been a massive challenge, from a QS perspective’. He points out the complexity of having to coordinate 140 procurement packages. “For us, that has been a big challenge, getting all of the procurement out and getting all the info from the architects.” CEC January 2018 - 17