The Civil Engineering Contractor February 2019 | Page 39

BUSINESS INTEL investments of regional significance that can provide adequate electricity supply to the region under different scenarios, in an efficient and economically, environmentally, and socially sustainable manner, and support enhanced integration and power trade in the SAPP region,” said Robinson. The PP incorporates the SAPP generation planning criteria published in 2011. The security criterion requires the minimum level of generation capacity to be equal to or greater than 100% of demand. The reliability criterion defines the reserve capacity obligation (10.6% of annual peak demand for predominantly thermal systems, 7.6% for mainly hydro systems, and weighted average for mixed systems). SAPP permits the reliability criterion to be met through a country contracting reserve auxiliary services from others. The conventional approach in a regional power sector master plan is to treat the interconnected region as though it were a single country and use optimisation planning software to derive the least-cost generation and transmission investment sequencing. However, an economically optimal regional plan is often not optimal from an individual country perspective due to other important non-cost factors. Robinson outlined the three principal case studies or components, with the third bringing in the factors of importance from individual country perspectives: •  Component A / Benchmark Case: This is a combination of country-by-country expansion plans based on national master plans extended (where necessary) to 2040 with a consistent set of assumptions. The results of this component are driven by two important assumptions: a large proportion of the generation options are defined by the countries as ‘committed’, and trade is limited by the only new transmission interconnectors allowed being those already under construction. • Component B / Full Integration Case: This is the full optimisation case whereby the region is treated as though it is a single country and a least-cost sequence of generation and transmission expansion projects is derived. •  Component C / Realistic Integration Case: This is an intermediate integration case, whereby certain constraints are applied to Component B to ensure that each country, at a minimum, fulfils SAPP security and reliability planning criteria. This was interpreted to mean that by 2040, each country should have sufficient installed or firm imported capacity to be able to meet its maximum demand and reserve obligations, and large thermal power plants should operate at or above minimum- capacity factor levels. The ministers ultimately selected Component C. Comparison of A, B, and C The executive summary of the SAPP PP 2017 describes the objective function as the optimisation “to minimise investment costs (overnight capital costs discounted from the year of commissioning), short-term operational costs (fuel and O&M costs), plus the cost of unserved energy (calculated at a notional cost of USD1 000/MWh) using a social discount rate of 6%. “The NPV of the total costs is the main indicator that can be used to rank the three components. Component B, the idealised Full Integration Case, is clearly superior to Component A, the Benchmark Case. To meet the demand forecast, only 127GW of installed capacity is needed in B as compared with 143GW in A. There is a significant saving in Panel discussion at a workshop hosted by SAPP in November 2018. www.civilsonline.co.za CEC February 2019 | 37