COTTON
GIN RENOVATION
EXCELLENCE IN CONSTRUCTION - MERIT WINNER
The extensive renovation of an eighty year old facility to provide new offices, gathering spaces, historical
landmark, and banquet hall. The project included remediation, installation of new concrete foundations,
upgrading the existing structure, interior finishes, exterior facade, and the dismantle and reconfigure of
the original 1936 cotton gin. The original building had selective demolition and pieces were salvaged
to be reused. There were two lean-to structures that were fully demolished due to structural damage. A
new garage was built on the back of the property as well.
6,545 HRS
Teal Total Man Hours
= 1,000 HRS
Specialty Contractor Total Man Hours
N
BCO TRACT
SU
42%
ER
LF P FORM
SE
S
32,341 HRS
58%
“
Custom Built Wood Value Engineering Savings
$308,707 Approximately 17% of
original contract.
”
The value engineering savings allowed the Owner to
incorporate additional upgrades to the scope of work.
PM: John LeBlanc & John Shead
E: Dave Ogden
Super: Benny Hopper
PC: Connie Enmon