Surface World May 2020 Surface World May 2020 | Page 48

TESTING & MEASUREMENT Furthermore, if the hose is worn and flexible, the air passing through will become more turbulent, thus adding to frictional losses along its length. Therefore, the most influential way a blaster can reduce pressure loss within the blast hose is by preserving its condition. Whilst minimising pressure loss may be sufficient to improve efficiency in smaller scale blasting projects, a larger project may require further adjustments. A blaster should therefore consider the combination of the compressor pressure setting, compressor air flow capacity, blast pot type, blast hose length and nozzle size. The blast nozzle is the single most important part of the blast system, designed to accelerate airflow to provide the abrasive with enough energy to clean or profile the surface being blasted. Hence, it is critical to use the optimum nozzle for the project being considered. The majority of blast work is completed using the inherently efficient single Venturi design, nozzles are available with a double venturi design, as well as different bore or orifice sizes. A nozzle with a larger orifice is thought to consume more abrasive and more air, causing blasters to have initial concerns about using larger nozzles. However, increased nozzle sizes enable larger spray patterns to be created. This means a larger surface area can be blasted in a shorter period of time, resulting in faster blasting, reduced air and abrasive consumption. As the nozzle size increases, the pressure at the nozzle drops meaning abrasives impact the surface with less kinetic energy. To counteract this pressure loss, a blaster can increase the pressure at the compressor. A larger orifice size enables more air to exit the nozzle which, without sufficient air volume capacity to support the higher air flow, causes the nozzle’s pressure levels to fall, resulting in reduced blasting efficiency. Therefore, air must be replenished to enable the blaster to achieve the required blast efficiency. This can be achieved by using a compressor which has a sufficient volumetric flow rating (usually CFM or LPM) capable of increasing the air flow to create the required pressure level at the nozzle. There is a big misconception that ‘driving’ a larger nozzle with increased CFM is more costly. In reality, the expenditure of a blast project can be reduced significantly by incorporating the suggested changes. By increasing the nozzle size and maintaining the optimum nozzle pressure, a blaster can achieve significant improvement in coverage speed, resulting in reduced fuel and abrasive costs per metre. Consequently, the labour, abrasive and equipment expenditure fall at a rapid rate. The advantages of incorporating this suggested change were highlighted in the 46 MAY 2020 testing commissioned by Elcometer. Elcometer Abrasive Blast Machines were used to blast a series of steel panels coated with a 3 layer glass flake epoxy, using three Each surface was coated with a tough 3-layer glass flake epoxy prior to testing. different compressor pressures (8, 10 &12bar), three different Single Venturi nozzles (#4¼”/6.35mm nozzle, #6 3 / 8”/9.5mm nozzle, #8½”/12.5mm nozzle) and air supplied by a 550 CFM 12bar rated diesel compressor, to a minimum of SA2.5 and a profile of 60-70 μm. The amount of time taken to blast a predetermined area of 1m2 would then be recorded, before each machine was weighed to assess the amount of abrasive used. Parallel tests were also carried out on a range of competitor blast machines and the performance differences were measured and recorded. The testing of various different pressure settings and nozzle combinations highlighted that higher compressor pressures with larger nozzles were blasting the surface significantly quicker than lower compressor pressures. In fact, the set-up widely adopted by the industry, consisting of 8 bar compressor pressure with a 3 / 8” nozzle, took 6.93 minutes to blast an area of 1m2. Yet, the optimised 12bar compressor pressure with a ½” nozzle set up took just 4.42 minutes to cover the same area - a 36% reduction in time. The amount of time taken to blast an area of 1m 2 was recorded during testing. CONTINUED ON PAGE 48 twitter: @surfaceworldmag