Surface World March 2020 Surface World March 2020 | Page 66

PAINT & POWDER The suction area covers almost 80 m², dry separation in the underfloor area is carried out vertically over both long sides of the unit with 192 edrizzi ® boxes. The secondary filtration stage was installed just behind the dry separation, taking into account an air slowdown zone to ensure clean air. Long service lives and flexible application The plant is operating in supply and exhaust air mode, with an exhaust air quantity of 100,000 m³ / h at a pressure of 1200 Pa. The application is done manually with high-pressure pumps by Graco. 2000 litres of surface material are processed per month. The plant runs in 2- or 3-shift operation, the paint mist separator achieving a service life of up to 16 weeks. Apart from economic, ecological and ergonomic benefits, the edrizzi ® system also convinces through flexibility. When the surface material is changed, as recently carried out at Liebherr Nenzing, the type of paint mist separator can be changed quickly and flexibly. So the plant was recently adjusted from edrizzi ® vario medium to edrizzi ® vario rough. Customer benefit: the economical, profitable and ecological painting Dry separation is more sustainable than wet scrubbing as it avoids using water & chemicals, and significantly reduces energy costs. The unrivalled high absorption capacity of the original edrizzi ® system of up to 100 kg / m² allows an extremely long service life, even in three-shift operation. The modular system means that replacing and disposing of the paint mist separator requires considerably less time and effort. In most cases, the saturated edrizzi ® boxes are inexpensively disposed of in incinerators. www.edrizzi.com Futher investment for Vertik-Al The latest stage of investment by Vertik-Al saw the installation of a second Magic Compact horizontal powder coating plant at the company’s Birmingham- based facility, in 12 months. Commissioned at the end of January, the new line is already showing improvements in powder consumption and efficiency. The quality of the application and finish of matt, gloss and textured coatings is excellent. The new powder coating plant was purchased from Gema UK as part of Vertik-Al’s continuous investment strategy and programme of asset management. Speaking on behalf of Gema UK, business manager, Leon Hogg said: “We are pleased to have installed a second advanced solution into Vertik-Al. The project was delivered, installed and commissioned in under 10 64 days, and allowed Vertik-Al to maintain delivery continuity to their customer base. “The benefits from the new plant were obvious from the start, the new control system is a pioneering interface for Smart Factory and offers excellent data visibility for the production team, this promotes line optimisation allowing Vertik-Al to work extremely efficiently, without compromise. The advanced automation of the powder recovery circuit delivers the fastest colour change in its class, alongside stable powder output.” Approved Coated Aluminium. It is also one of a handful of applicators to boast membership of the product certification scheme, QUALICOAT. Visit www.vertik-al.com to discover how your business can benefit from Vertik- Al’s latest investment and over 50 years’ experience in powder coating. Vertik-Al remains the only applicator in the UK and Ireland to hold the GSB International quality seal for MARCH 2020 twitter: @surfaceworldmag