WORK STARTED ON EAST-NAKHODKA TRANSPORT HUB
The Summa Group’s Stroynovatsiya has started working on the development of the East-Nakhodka
Transport Hub in Primorsky Krai. The public-private partnership sees Stroynovatsiya LLC build the
new port infrastructure at Vostochny Port, as ordered by FKU Rostransmodernizatsiya.
Plans include integrating railway approaches and a new coal terminal in the transport hub. The
overall infrastructure will include an extension of the railway track by 50 kilometres, 11 bridges and
overpasses and four berthing facilities reaching a total length of 900 meters.
Stroynovatsiya will reconstruct the current
infrastructure, which will allow for dredging
operations and see geodetic survey works.
With more than 1400 people working on the
project and 15%, at least, of the work being
given to local subcontractors, the project is
scheduled to be completed in late 2017.
FESCO – NCSP - STROYNOVATSIYA – INTEX – YATEC – UNITED GRAIN COMPANY