SERVICES
• Constructability consultation
• Prefabricated and field-fabricated
construction
• Prefabricated horizontal construction
• Diked construction and tank
installation
• Double-wall construction and tank
installation
• Total renovation
PROJECT SPOTLIGHT
Ruby Fuel Storage Facility
In 2009, the Alaska Energy Authority (AEA)
commissioned the complete renovation of
the bulk fuel storage facility in Ruby with
two main objectives: to construct a new
facility and to maintain operations of the
existing one. However, the new facility had
to be built in almost the exact same spot as
the one it was replacing.
It was crucial for construction of the new
facility to finish in time for the final fuel
shipment of the season. STG designed and
rapidly executed an effective work plan to
ensure that Ruby’s 180 residents had a
place to store fuel before winter—STG
finished construction in one summer.
Ruby can now store 30,000 gallons of
gasoline and 130,000 gallons of diesel
fuel year-round.