The Sewer System Improvement Program (SSIP) is a critical citywide investment
in our people, our communities, and our quality of life.
The Program
DISTRICT 3
DISTRICT 2
DISTRICT
5
DISTRICT 6
DISTRICT 1
The SSIP is divided into three
overlapping phases to maintain
affordability. To date only Phase 1 has
been approved by our Commission
representing $2.9 billion. This first
phase is comprised of 70 grey and
green projects all over the City.
Grey. Upgrades to our pipes and
Treatment Plants for reliability,
resiliency, and regulatory compliance.
DISTRICT 8
Green. Innovative stormwater
management tools that not only reduce
impacts to our system but, help beautify
our neighborhoods too!
DISTRICT 4
DISTRICT
9
DISTRICT 7
DISTRICT 10
Clean. Improving our infrastructure to
protect the health of our communities
and the environment.
DISTRICT 11
This map depicts the approximate
locations of our Phase 1 projects
Treatment Plant Upgrades
Central Bayside System
Improvement Project
Green Stormwater
Management Projects
Flood Resilience Projects
Large Sewers, Tunnels,
and Odor Control Upgrades
Pump Stations and Force
Main Improvements
Interdepartmental
Projects
sfwater.org/ssip
Combined Sewer
Discharge
Structures and
Transport/Storage
Boxes Improvements
Phase 1 of the SSIP is currently 19.2% complete;
with approximately 16% of the budget spent.
Many opportunities still exist!
Learn more about the SSIP and all of the Phase 1 projects at sfwater.org/ssip
$2.9 BUDGET
Billion
$463M
SPENT