Sirena Swimwear Sirena Swimwear | Page 43

WEEK 1; Range Plan Meeting

WEEK 2; Create Range Plan & Budget

WEEK 3; Design Range

WEEK 5; Lab Dip Colours

WEEK 6; First Sample

WEEK 7; Range Selection

WEEK 8; Range Review Meeting

WEEK 8; Negotiate Prices/Deliveries

WEEK 8; Orders Places Far East

WEEK 9; Fit Samples

WEEK 11; Approve Fabrics/Colours

WEEK 12; Fabric Trim/Productions

WEEK 15; Seal Garments

WEEK 16; Cut Date

WEEK 21; Approve Production Samples

WEEK 22; Order Shipped

WEEK 25; Plan Allocation

WEEK 26; Order Arrives

WEEK 26; Ready To Be Sold Online

DATE

16th OCT '18

23rd OCT '18

30th OCT '18

13th NOV '18

20th NOV '18

27th NOV '18

4th DEC '18

4th DEC '18

4th DEC '18

11th DEC '18

25th DEC '18

1st JAN '19

22nd JAN '19

29th JAN '19

5th MAR '19

12th MAR '19

2nd APR '19

9th APR '19

9th APR '19

PEOPLE RESPONSIBLE

B&M Director, Buyer, Merchandiser, Designer

B&M Director, Buyer, Merchandiser

Designer

Buyer, Designer, Garment Technician, Supplier

Designer, Supplier

Buyer, Merchandiser

Buyer, Merchandiser

Buyer, Merchandiser, Supplier

Buyer

Buyer, Garment Technician

Garment Technician

Garment Technician

Buyer, Garment Technician, Supplier

Buyer, Supplier

Garment Technician

Supplier

Allocator

Supplier

Website Coordinator