WEEK 1; Range Plan Meeting
WEEK 2; Create Range Plan & Budget
WEEK 3; Design Range
WEEK 5; Lab Dip Colours
WEEK 6; First Sample
WEEK 7; Range Selection
WEEK 8; Range Review Meeting
WEEK 8; Negotiate Prices/Deliveries
WEEK 8; Orders Places Far East
WEEK 9; Fit Samples
WEEK 11; Approve Fabrics/Colours
WEEK 12; Fabric Trim/Productions
WEEK 15; Seal Garments
WEEK 16; Cut Date
WEEK 21; Approve Production Samples
WEEK 22; Order Shipped
WEEK 25; Plan Allocation
WEEK 26; Order Arrives
WEEK 26; Ready To Be Sold Online
DATE
16th OCT '18
23rd OCT '18
30th OCT '18
13th NOV '18
20th NOV '18
27th NOV '18
4th DEC '18
4th DEC '18
4th DEC '18
11th DEC '18
25th DEC '18
1st JAN '19
22nd JAN '19
29th JAN '19
5th MAR '19
12th MAR '19
2nd APR '19
9th APR '19
9th APR '19
PEOPLE RESPONSIBLE
B&M Director, Buyer, Merchandiser, Designer
B&M Director, Buyer, Merchandiser
Designer
Buyer, Designer, Garment Technician, Supplier
Designer, Supplier
Buyer, Merchandiser
Buyer, Merchandiser
Buyer, Merchandiser, Supplier
Buyer
Buyer, Garment Technician
Garment Technician
Garment Technician
Buyer, Garment Technician, Supplier
Buyer, Supplier
Garment Technician
Supplier
Allocator
Supplier
Website Coordinator