SA Affordable Housing May - June 2020 // ISSUE: 82 | Page 10

NEWS Quality hollow-core slabs for large low-cost housing project Quality hollow-core slabs for large low-cost housing project Located along Railway Street a large low-cost housing project in Polokwane, Annadale Phase 2 comprises just more than 17 000m² of development. It consists of 11 double- and triple-storey apartment blocks to provide 500 additional low-cost housing units, including 30m² one- and 40m² two-bedroom units, in this growing urban hub by February 2022. The project is being driven by the Polokwane Housing Association, a division of the Polokwane Municipality and managed by multidisciplinary consultant, Chiefton Consulting & Services. By the beginning of 2020, Motheo Construction Group, the principal contractor, was already forging ahead on the construction of the first four apartment blocks. CoreSlab, a leading South African precast-concrete specialist is supplying a total of 16 000m² of hollow-core slabs (HCS) to the project. A decision was taken by the professional team to modify the initial design to incorporate HCS as opposed to rib-and-block technologies to significantly accelerate the project and reduce construction costs. CoreSlab was involved in the design of the HCS floor slabs to ensure its swift approval by the National Home Builders Registration Council. A decision to use HCS also proved to be more cost-effective than rib-and-block systems, considering the savings in equipment and construction materials. More than 300 people will be employed on the construction site when work commences on the roof structures in April 2020. By February 2020, there were already 200 people employed on the construction site. They include the five bricklaying teams, each comprising 12 skilled bricklayers and 18 general workers per subcontractor. The HCS are dispatched to site on a just-in-time basis and then lifted directly from CoreSlab’s truck trailers using a mobile crane, with the team moving from one block to the next according to a predetermined schedule that is determined by the principal contractor on a weekly basis. CoreSlab was also contracted to manufacture and install all precast concrete stairs– a sizeable undertaking considering that there are four flights per level for each of the 11 residential blocks. Moreover, CoreSlab, is undertaking all core drilling services. 8 MAY - JUNE 2020 SAAffordHousing saaffordablehousingmag SA Affordable Housing www.saaffordablehousing.co.za