SA Affordable Housing May / June 2017 // Issue: 64 | Page 17
CONTRIBUTORS
DEFECTS LIABILITY PRIOR TO PRACTICAL
COMPLETION
Practical completion is defined in the JBCC as:
‘The stage of completion as certified by the principal agent
where the works or a section thereof has been completed
free of patent defects other than minor defects identified
in the list for completion and can be used for the
intended purpose.’
The most important ‘performance date’ is when the date
of practical completion has been attained. Thereafter the
employer may occupy the building in accordance with the
predetermined timeline. In terms of the JBCC it is of great
importance that the work meets the required standards at
the date of practical completion. Therefore, the principal
agent, together with other agents and the contractor are
encouraged to work ‘as a team’ towards achieving this goal.
Where the work fails meet the required standard as
mentioned, the principal agent is obliged to issue a
comprehensive list of defects that need to be repaired. A
competent and eager contractor must be given the
opportunity to repair its defective work. If the contractor
fails to remedy the defective work within a period of five
business days of being notified, the employer may invite a
third-party contractor to repair same. The employer must
always try to mitigate the contractor’s loss by affording it
the opportunity to repair its defective work. Generally, the
employer’s damages will be limited to the costs of repair to
bring the project to practical completion.
DEFECTS LIABILITY DURING THE DEFECTS
LIABILITY PERIOD
The defects liability period starts on the calendar day after
the date of practical completion and ends at midnight 90
calendar days from the date when practical completion has
been reached or when the work on the list for final
completion has been completed to an acceptable standard,
whichever is the later. After practical completion has been
attained, the principal agent shall issue the list for
completion to the contractor.
The list for completion is defined as:
‘A list by the principal agent where practical completion
has been certified, listing defects and/or outstanding work
to be completed.’
The principal agent may only issue one list for
completion, however if other defects become apparent
during the defects liability period, the principal agent may
instruct the contractor to repair same.
Final completion is only achieved after a minimum of
90 calendar days following practical completion to afford
the contractor the opportunity to remedy all items on the
list including latent defects not apparent at the date of
practical completion.
The list for final completion is defined as:
‘An updated list for completion issued by the principal
agent after the inspection of the works for final
completion, where final completion has not been achieved,
listing defects and/or outstanding work to be completed to
achieve final completion.’
Final completion is defined as:
‘The stage of completion of the works as certified by the
principal agent as being free of defects.’
After the final completion certificate has been issued it
means that the contractor has fulfilled all its duties in
terms of the contract, not including latent defects. The
careless issuing of a final completion certificate by the
principal agent may lead to a claim for professional
negligence against the principal agent. An employer has no
claim against the contractor for defective work after the
final completion certificate has been issued, because once
it has been issued it cannot be amended or withdrawn. The
certificate can only be disputed on limited grounds, for
example, fraud or where he acted beyond his powers.
DEFECTS LIABILITY AFTER THE ISSUING OF THE
FINAL COMPLETION CERTIFICATE
Once final completion has been reached all of the
contractor’s obligations have been fulfilled other than
latent defects. A typical example of a latent defect is
inadequate foundations causing subsidence of
the building.
The contractor’s liability for latent defects is limited to a
period of five years from date that final completion has
been attained. An employer is obliged to institute action
against the contractor to rectify defects within three years
from the date on which he becomes aware of the defects or
could reasonably have become aware of the existence of
the defect, failing which the claim prescribes.
The contractor’s obligation for damages regarding
defective work claims is not terminated by the issuing of a
final completion certificate and the contractor is still
obliged to repair all latent defects that become apparent
during the latent defects liability period.
A competent and eager contractor
must be given the opportunity to
repair its defective work.
Construction Law Specialists
Email: [email protected]
www.endvdm.co.za
Cape Town:
Bella Rosa Village,5th Floor,
Modena Building, 21D Durbanville
Avenue, Rosendal, Bellville
Tel: 021 914 0770
Johannesburg:
1st Floor Bradford Cnr, 2 Bradford
Rd, Bedford Gardens
Tel: 011 615 8591
AFFORDABLE
SA HOUSING
MAY - JUNE 2017
15