Rice Business Report December 2019 Edition December 2019 Rice Business Report | Page 8
Rice Business Report
December 2019
Segment I-2
SH-146 in Mont Belvieu to SH-99 in Baytown
Crews continue to work on the frontage roads and bridges in
segment I-2. Over the coming weeks and months, the team
will be focusing on:
Installation of drainage structures along SH-146 and SH-99.
Removal of the lift bridge in Baytown on the Cedar Bayou is
scheduled for mid-November 2019, weather permitting. Dur-
ing this time, there will be no access to through traffic on the
bayou at the lift bridge location.(photo)
Drilling shafts, pouring caps, and setting beams for the bridge that will be
constructed over IH-10
Introducing Chris Neil......
Grand Parkway Infrastructure would like to welcome Chris Neil. He joins us
as the new Public Relations Manager for the Grand Parkway Infrastructure
project, segments H, I-1, and I-2. Please do not hesitate to reach out to Chris
with any questions about the project, or if you'd like to setup a meet and
greet. He is excited to get involved in the local communities impacted by
the project and be a liaison for construction updates.
[email protected]
(877) 553-7374
8