was monitored following hot work activities. Completed documentation must be signed and submitted in accordance with Renown Health procedures before the Hot Work Permit can be closed.
The fire watch must have no other assigned duties, be trained in the use of fire extinguishers, understand emergency alarm procedures, and remain alert for sparks, slag, or other signs of fire. Hot work performed within 35 feet of combustible materials requires a minimum one-hour fire watch after work is completed. All penetrations must be covered, combustible materials protected or removed, and appropriate fire-resistant barriers provided. Fire watches are responsible for responding to small fires, activating alarms when necessary, and documenting completion of the fire watch on the Hot Work Permit. Additional fire watch monitoring may be conducted by Hospital Security following completion of hot work. Special precautions and written procedures are required for hot work involving pressurized equipment, flammable systems, or other high-risk conditions.
Hydrostatic Testing Standard / Procedure Hydrostatic testing is used to verify the integrity and leak-tightness of piping systems, pressure vessels, and related equipment. All hydrostatic testing must be performed in accordance with approved engineering procedures, applicable ANSI / ASME codes, and project-specific requirements. Prior to testing, contractors must submit a site-specific hydrostatic testing procedure for review and approval, ensure proper communication with affected personnel, and establish controls to protect people and property. Test areas must be restricted, clearly marked with warning signage, and equipped with properly calibrated test equipment, pressure gauges, relief devices, and secure hose connections. Contractors are responsible for verifying system readiness, structural support, spill prevention measures, and safe operating conditions throughout the test. During testing, all flanges, fittings, and connections must be properly installed, and adjustments or tightening of pressurized systems are prohibited. Hydrostatic testing must be conducted using approved procedures to ensure safety, regulatory compliance, and protection of personnel and facilities.
Fired Heaters Standard / Procedure Fired heaters used to heat air or liquids must be operated safely to prevent fires, explosions, and other hazards. Direct-fired heaters are prohibited in or near facilities and may only be used in limited circumstances with appropriate approval. Indirect-fired heaters may be used when positioned and operated in accordance with safety requirements. Heaters located near occupied areas or connected to hazardous locations may require a Hot Work Permit. All associated duct work must be flame-resistant and free of combustible contamination. Fired heaters must have clearly posted emergency shutdown procedures and be equipped with, or located near, appropriate fire extinguishing equipment. Contractors are responsible for monitoring heater operation, maintaining safe separation from ignition sources and combustible materials, considering wind direction and ventilation conditions, and conducting routine inspections for leaks, fire hazards, or unsafe conditions. Regular inspections and prompt corrective action are required to ensure safe operation throughout the duration of use.
Excavation, Trenching, and Drilling