Renewable Energy Installer April 2015 | Page 32

Knowledge: District heating In the pipeline With cost remaining a key barrier to the deployment of district heating systems, the sector must optimise design to reduce cost and improve efficiency, explains REHAU Renewable Energy’s business team manager, Steve Richmond he UK has the potential to become Europe’s fastest growing district heating market – the government’s Heat Strategy supports public sector investment in district heating and the Renewable Heat Incentive is proving a key driver in communal renewable heating systems. However, capital costs are often a barrier for district heating schemes and the crucial challenge facing those of us within the industry is to ensure that more of the heat networks being installed in the future are optimised so that both costs and heat losses are reduced. For installers operating in this sector, there are four main areas which I would advise to concentrate on – sizing the correct heat load, optimising the flow/return temperatures, using diversity and reducing installation costs. Using these four key messages on a district heating project of 50 houses and a 1.5MW central plant for example, REHAU’s technical team were able to reduce the original material list price by over 50 percent simply by efficient network design. On retrofit communal heating schemes, there can be a temptation to estimate heat loads for individual dwellings which can often lead to overestimating the total heat load. The resulting impact of this is the installation of an inefficient system and a reduction in income for the scheme operator who is selling the heat. Probably the greatest impact on capital costs comes from successfully optimising the flow and return temperatures within the system. In simple terms, the greater the delta T (difference in flow/return temperatures), the smaller the pipe size required. Using a 450kW example heat load and 82/71ºC, a 110mm (OD) pipe size would typically be recommended. However, if you can reduce that return temperature to just T 32 | www.renewableenergyinstaller.co.uk 50ºC, then the pipe size would only need to be 75mm. With pipe materials accounting for upwards of 50 percent of the installed network cost, any savings made in materials can be significant. Another option is to use heat pumps linked to district heating which operate at lower temperatures and hence have lower transmission heat losses. This has significant potential in the UK, particularly using waste heat from infrastructure or industry. Reducing the return temperature will also significantly reduce heat losses. For example, using 1km of RAUTHERMEX and the original 110mm pipe sizing at 82/71ºC as the benchmark, we can show that by using 90mm at 80/60ºC instead, you reduce those losses by 25 percent and, by reducing the pipe size still further to 75mm with a 50ºC return temperature, you reduce the losses by 43 percent. Diversity of a heat network is an important topic as it has a large impact on the size of the central plant. Diversity is the likelihood of all heat customers using their heat load at the same time. For small systems below 10 dwellings it might not be relevant but for larger networks, it can have a large impact on the total heat load and hence the pipe sizing. REHAU has produced bespoke calculation software to help calculate the estimated diversity of heat networks. There can be a temptation to estimate heat loads for individual dwellings which can often lead to overestimating the total heat load Fantastic four: Installers should focus on correct sizing, optimising flow/return temperatures, using diversity and reducing costs for the sector to flourish, says Steve Richmond, REHAU Renewable Energy’s business team manager Steel pre-insulated pipes have been commonly associated with district heating schemes but the market trend for lower temperatures is now favouring polymer pipes such as REHAU’s RAUTHERMEX and RAUVITHEM due to their high flexibility, low heat losses and long coil lengths which overall make them more cost effective to install than steel. In many projects, it is also often possible to use twin rather than single pipe which works out cheaper than doing two separate pipe runs and actually has up to 40 percent lower heat losses overall. Innovative pipe routing and optimising tee connections can also help reduce costs.