Phase 3 progress details:
• Phase 3 network opened so far: 62 kilometres |
Sl. No |
Corridors opened |
Kilometres |
1 |
Central Secretariat – Kashmere Gate |
9.37 |
2 |
Badarpur – Escorts Mujesar |
13.975 |
3 |
Jahangirpuri – Samaypur Badli |
4.489 |
4 |
Durgabai Deshmukh South Campus – Majlis Park |
21.56 |
5 |
Botanical Garden – Kalkaji Mandir |
12.64 |
• Phase 3 kilometres after the opening of this section: 87 kilometres
• Phase 3 network yet to be opened after the opening of this section: 72 kilometres( Excluding NOIDA – Greater NOIDA section)
Sl. No |
Corridors to be opened |
Kilometres |
1 |
Durgabai Deshmukh South Campus – Shiv Vihar |
9.37 |
2 |
Mundka – Bahadurgarh |
13.975 |
3 |
Noida City Centre – Electronic City |
4.489 |
4 |
Dwarka – Najafgarh |
21.56 |
5 |
Escorts Mujesar – Ballabhgarh |
12.64 |
|
Dilshad garden – New Bus Adda |
|
Connectivity highlights:
The opening of the Janakpuri West – Kalkaji Mandir section of the Delhi Metro will immensely improve the connectivity of the national capital. With the opening of this corridor west Delhi, south Delhi and the satellite city of NOIDA will get interconnected like never before. The entire Magenta Line from Janakpuri West to Botanical Garden will be served by four interchange stations –
• Janakpuri West( with Blue Line)
• Hauz Khas( With Yellow Line)
• Kalkaji Mandir( with Violet Line)
• Botanical Garden( with Blue Line)
The main connectivity highlights will be as follows: www. railanalysis. com