Measurements included:
• line voltages
• phase balance
• compressor currents
• fan motor currents
• chilled water temperatures
• system pressures
• compressor loading
• controller operating parameters
Performance observations showed that, under the prevailing low building load and weather conditions, the second compressor modulated to approximately 22 % load, demonstrating the effectiveness of the variable-capacity control strategy.
Operational benefits: The completed installation provides several measurable operational improvements.
Improved energy efficiency: Variable-speed screw compressors provide excellent seasonal efficiency.
Improved reliability: Redundant plant configuration significantly reduces operational risk.
Reduced maintenance: Modern equipment requires substantially less routine maintenance than the original installation.
Improved plant control: Modern controllers provide accurate capacity modulation and comprehensive fault diagnostics. Future flexibility: The primary-secondary configuration provides a robust platform for future building modifications or tenant changes. project
PHASE 2 Following successful operation of the Phase 1 installation, the remaining existing plant was removed.
Phase 2 included:
• installation of the second chiller
• completion of the hydraulic headers
• commissioning of the complete duty arrangement
• final balancing
• optimisation of the control strategy This staged implementation avoided prolonged building shutdowns while progressively increasing available cooling capacity. The project reached final completion in June 2026, with RPM Consulting Engineers certifying the works for the Chiller Upgrade Phase 2.
LESSONS LEARNED Several important engineering lessons emerged from the project:
• Early construction sequencing is critical.
• Temporary cooling strategies should be developed during design.
• Nitrogen pipe freezing is highly effective where shutdowns are unacceptable.
• Primary-secondary pumping provides considerable operational flexibility.
• Variable-speed screw chillers deliver excellent part-load efficiency for commercial office buildings.
• Comprehensive commissioning is essential to realise the full performance potential of modern HVAC systems.
Supplied by RPM Consulting Engineers
Figure 5 – Completed Phase 2 chilled water plant.