RENEWABLE ENERGY
“ In our own experience bringing a wind farm to financial close, we were required not only to spend years on technical and commercial development, but also to demonstrate substantial personal net worth and directly-fund guarantees and advisory fees. It is not uncommon for project sponsors to spend R10-million or more of their own money before lenders are prepared to commit. The consequence is that only those with pre-existing wealth, or access to it, can realistically sponsor infrastructure projects at scale.
“ Layered on top of this is a localisation challenge we have not yet been willing to confront honestly. When localisation is discussed – whether for PV modules, transformers or other components – the immediate response is that local producers cannot compete with Chinese prices. That is true on a narrow price comparison: Chinese manufacturers benefit from scale, industrial ecosystems and state support,” he said.
He describes“ the deeper question” as being whether South Africa is prepared to pay the real price of transformation. A locally manufactured component, produced under South African labour and environmental conditions, will often cost more than its imported equivalent. If all procurement is awarded purely on lowest price, localisation will almost always lose. IPPs offering rock‐bottom tariffs in competitive tenders cannot absorb a significant local premium.
“ At the same time, we have seen government move quickly to subsidise energy for large corporates – such as the 62c / kWh support for smelters – to prevent closures and job losses. That shows the state is willing to use the national balance sheet creatively when the political will exists.”
Imagine if similar creativity were applied to localisation: mines and big users accepting slightly higher tariffs, with the uplift explicitly ring‐fenced for local manufacturing and enterprise development; government matching that uplift with incentives;
and IPP procurement rules that reward genuine local content and ownership in ways lenders can bank.
WHERE THE OPPORTUNITY STILL LIES Despite these structural concerns, there are promising opportunity domains for engineers, developers and entrepreneurs who want to help shape a better system.
One is energy trading and project indexing. As private wheeling and energy exchanges grow, off‐takers will need trusted information on real, bankable projects. A national renewable project index, with standardised due‐diligence and transparent data, would make it far easier for corporates to contract with legitimate generators and for lenders to assess risk.
Another is AI‐assisted legal and technical services. Today, legal and technical due diligence absorbs months and millions, even though most PPAs, EPCs and O & M contracts are variants of familiar templates. AI tools could rapidly flag non‐standard clauses, test bankability and highlight technical risks, dramatically lowering transaction costs – especially for smaller projects.
A third is the evolution of Eskom towards a wires‐focused role. As generation becomes more distributed, opportunities will expand in grid support services, ancillary markets and embedded solutions tied to transmission and distribution networks.
Finally, demand‐side management and IoT will be central in a high‐renewables system. Smart meters are just the beginning. Networks of controllable loads – HVAC systems, refrigeration, industrial drives and building management systems – will give system operators new tools to balance the grid. For engineers and technologists, the challenge is to design systems that are not only efficient, but can respond intelligently to grid conditions and price signals. RACA business
Part of the presentation.