Project
Another view of the modified installed plantroom. will be accommodated in Luanda for the duration of the project( 16 months) commencing 15 February 2024:
• Ar Azul Projects – major mechanical work and installation
• Infinity Technical Services – BMS, controls and electrical works
• Pictech( Pty) Ltd – chillers; repairs and final commissioning
• Bitzer South Africa – compressors; supply and plantroom installation works
• Skyshot – CIAT equipment; inspections, commissioning and final reports
In addition, full training will be given to the client’ s site maintenance staff with regard to the servicing of all plant, BMS controls operation, etc. supported by remote access facilities received from South Africa.
The final objective is to accomplish a further 15 – 20 years of reliable, maintenance friendly, safe and cost-effective plant operation for the new owners going forward.
RPM MD Barry Wallett says:“ As RPM’ s largest HVAC refurbishment project to date, we are well aware of the challenges facing us when carrying out work of this nature beyond our borders. Nevertheless, we have selected a highly skilled and experienced contracting team to facilitate the work. As such, we are looking forward to a successful project. In doing so, we furthermore aim to showcase the high standard of South African engineering expertise, commitment and integrity.”
HVAC REFURBISHMENT IN LUANDA, ANGOLA RPM Consulting Engineers, a division of the RPM Engineering Group, has embarked on its most ambitious project to date: the comprehensive refurbishment of HVAC systems in a