Project
20-year-old box . Once he realised the
context , he doubly appreciated the
work we had done .”
Kleyn explains that the
refurbishment project is designed to
tackle several key issues , with a primary
focus on reducing costs , enhancing
environmental sustainability , and
improving operational efficiency . “ One
of the main reasons for refurbishing the
air conditioning systems is to provide
significant cost savings compared
to replacing the entire unit ,” he
explains . By refurbishing , they aim to
retain some components , effectively
Water cooled package unit converted to latest Pick n Pay specifications .
‘ recycling ’ materials rather than simply
In situations where full shutdowns are required , such as
discarding them .
during the peak summer season , Elmec carefully schedules
When asked how Elmec ensures refurbishments don ' t disrupt
the refurbishments to minimise disruption . “ We ensure
Pick n Pay ’ s daily operations , Kleyn points to the importance of the
that we do most of the heavy lifting during off-peak hours ,
preparation phase . “ A significant portion of the work can be done
often in the evenings ,” he explains . This careful scheduling
while the existing systems are still operational ,” he says . Most units they encounter are already partially failed , allowing Elmec to start preliminary work without affecting store performance .
“ By using the available space in plant areas , we can install new condensing units and complete much of the pipework in advance . This way , by the time the new coils arrive , we ’ ve already done about 50 % of the work .”
allows for seamless transitions with minimal downtime .
Kleyn also highlights the innovative LG Smart 5 controller , which significantly boosts the functionality of the refurbished systems . " This versatile controller simplifies programming and enables real-time monitoring ," he explains . The tablet-shaped device integrates seamlessly into the existing infrastructure ,
allowing technicians to manage and program the system
without needing specialised software expertise .
The LG Smart 5 controller offers a wide range of inputs
and outputs , delivering both flexibility and complete
oversight of the refrigeration system . " It allows us to
monitor critical parameters such as refrigeration pressures
and system data ," Kleyn explains . This feature enables
Elmec ’ s technical team to remotely diagnose issues before
sending technicians to the site .
“ This off-site monitoring is a game-changer as a
standard feature without the addition of expensive
building management systems ( BMS ). Unlike traditional
systems where you can only check if a unit is on or off ,
the LG Smart 5 gives us detailed insights into system
performance . This means we can address potential issues
proactively , ensuring efficient operations for Pick n Pay .”
Coordination is vital in such a project . “ VMG takes
the lead on project management . They handle the
design aspect and oversee the overall quality throughout
the project . My role focuses on the installation and
communication with suppliers and manufacturers ,
ensuring everything runs smoothly .”