RACA Journal I July 2026 www. refrigerationandaircon. co. za 31
PROJECT project
All image supplied by VMG Consultants
Each plant room housed four packaged units.
In each plant room, four Midea ducted hideaway indoor units – each rated at approximately 28kW – are connected to the existing duct distribution system.
Installation required core drilling through the building envelope and the establishment of external distribution points along the façade.
Electrical boxes on each floor.
A rooftop view.
Project name:
Mineralia Building
List of professionals:
Name of company
Project manager
VMG Consultants
Consulting engineer
Mechanical
VMG Consultants
Contractors
HVAC & R
Javess Tab Services
Product suppliers
Product
Supplier
VRF system
Midea
Fresh Air Fans
Luft
Background image supplied by VMG Consultants