Projects
1
Continued from page 53
FINISHING UP
2
The refurbishment project will be
concluded during the 2018/2019 season.
This project is a fine example of the
work undertaken and successfully
concluded by DPW, their consultant
Royal HaskoningDHV, and the
contractor Nolitha.
The final product will ensure the
successful operation of the base for the
next 20 years. RACA
1.
2.
New pipeline to
base from snow
smelter.
New snow
smelter being
installed.
LIST OF PROFESSIONALS
Owner / client Department of Public Works
End user Department of Environmental Affairs
Developer Department of Public Works
Project manager Department of Public Works
Consulting engineers Electrical, mechanical, wet services,
structural, and civil Royal HaskoningDHV
Contractors Main building, HVAC&R, wet services,
and electrical Nolitha
Gensets CAT
Effluent plant Martin Membrane Systems
Vacuum drainage system Jets
Snow smelter TFD
Pumps Wilo
Controls CAS
BMS Johnson Controls
FCUs Air Options
Product suppliers
www.hvacronline.co.za
RACA Journal I January 2019