RACA Journal February 2022 | Page 45

www . hvacronline . co . za RACA Journal I February 2022 43
Project for this particular VRF system started to become difficult and got to the point where the hassles of this overshadowed the work that needed to be done , and a decision had to ultimately be taken on a replacement system .
" The product selection was based on meeting critical energy efficiency aspects ."
There were two options , namely a replacement VRF system or a chilled water system . The space constraints and challenges of the previous VRF system would result in similar future challenges , and the fact that there were not really many other options to hide or disguise the control boxes – even placement in the passageways was considered , but this would take away from the building features , so was declined .
Based on these multiple factors it was decided to rather select the chilled water system as the preferred replacement . Two chillers were installed in an allocated space at the back of the building ( the building courtyard ) where space allowed . The chiller platform was built at a higher level in the courtyard zone . The two chillers have a capacity of 200kW each . Fancoil units , with capacities ranging from 2.5 to 5.2kW were installed at various locations in the building .
The required piping installation was all done at the back of the building , entering into the building space from this point , and hidden in pockets , ceilings spaces ( where possible ) or the bulk heads . Everything pipe related was done from the back of the building ( back to front ) so that the building façade was not compromised in any way .
The product selection was based on meeting critical energy efficiency aspects , and the consideration of deploying an environmentally friendly refrigerant – in this case R410a . The chillers , having scroll compressors , have an EER of 2.13 , essentially meaning that they produce more than double an output capacity over the input energy . This type of efficiency was also not available in earlier years when the original restoration was done .
PROJECT CHALLENGES Some of the notable project challenges included the erection of scaffolding in the narrow courtyard area to complete the required work at the plant platform . This area is particularly unbalanced and special manoeuvring was necessary as no access other than manpower could reach this space .
Continued on page 45
The building foyer . The floor here is also protected by a specially designed glass ramp .

www . hvacronline . co . za RACA Journal I February 2022 43