RACA Journal February 2020 | Page 67

Contract savvy prejudice it may suffer if the subcontractor is not paid and/or exercises a lien over any of its works and materials provided probably that there has been no supervening liquidation of the contractor 14 , loss of manufacturers’ warranties and maintenance, etc. It is incumbent on the subcontractor to act swiftly and decisively to ensure that the employer has an interest in and elects to make direct payment by exercising liens, withholding product and other guarantees, rejecting any calls for liability for latent defects, encouraging the employer to continue to use the subcontractor’s services to complete the works without delays, and the like or alternatively, where the subcontractor is interested in completing the n/s works, by allowing the subcontractor to effectively add it to its price for completing the n/s works after termination. CLAUSE 38.5.8 ‘The security [14.5] shall expire and be returned by the employer to the subcontractor’. The security due in terms of clause 14.5 – advance payment guarantee - must be returned to the subcontractor. This guarantee is issued by the subcontractor to the employer specifically to cover the value of advances by the employer which would typically terminate when the principal building agreement is terminated but it is submitted that there would simultaneously have to be a form of delivery of all the goods covered by such advance payment guarantee. As the principal contract and the subcontract have been terminated the subcontractor no longer carries the liability for the n/s works and has no further interest in protecting them once delivered to the employer. This clause makes no reference to the n/s construction guarantee/retentions nor does it make reference to the payment guarantees due in terms of clause 3.1, both of which have been discussed under bullet 4 above. CLAUSE 38.5.9 ‘The latent defects liability shall end [27.2.2]’ According to Du Bois et al, Wille’s Principles of South African Law 15 at p. 945 the principles of contracts of locatio conductio operis in the Roman-Dutch common law provide that if the employer approves the opus, he absolves the builder from liability for all defects, latent as well as patent. A latent defect is defined in clause 1 as ‘a defect that a reasonable inspection of the n/s works by the principal agent would not have revealed before the issue of the defects list.’ The defects list is a list issued in terms of clause 26 Final Completion. Clause 27.1 provides for a latent defects liability period of 5 years from the date of the final completion certificate but sub-clause 27.2 distinguishes two different liability periods in the event of termination. Clause 38.5.9 therefore provides that the latent defects liability period ends on the date of termination in accordance with clause 27.2.2. 14 15 16 17 It is incumbent on the subcontractor to act swiftly and decisively to ensure that the employer has an interest in and elects to make direct payment. This provision can be used as a basis for negotiating direct payment or as a negotiating tool in establishing the cost of completing the n/s works. However, it is submitted that it does not displace the provisions regarding the terminated contractor’s obligation to ensure the work executed by specialised trades is correctly done 16 and an entitlement for the employer to recover any costs of making good defective work in the work completed prior to termination by way of a reduction to the value of the work completed 17 or by a claim for damages against the contractor (see also discussion under bullet 4). The purpose/consequence of the provision could be: 1. To provide a cut-off point placing the eventual latent defect liability on the new contractor completing the works as it is possible for this contractor to inspect the works, report work that is defective and obtain a contract instruction for the correction of the defect. 2. Alternatively, and possibly concurrently, it is also intended to provide the employer and principal agent with a cut-off which enables them to finalise and pay the n/s works final account leaving the liability for any unobserved defective work in the n/s works within the ambit of a reduction to the price for the principal contractor’s works final account or a recovery in the final payment certificate as between the contractor and employer and thereafter a final recovery statement adjustment as between the contractor and the subcontractor which is patently the correct place for these adjustments to keep the employer out of that [sub] contractual relationship. The further benefit of this latter interpretation is that the liability for correction of the defects then resides in its proper place and, insofar as it affects the employer, is subject to the principal building agreement’s termination provisions which differ between terminations resulting from either the employer’s or the contractor’s default. It is up to the subcontractor to price for this risk or to stipulate for any limitation to its liability in a subsequent agreement for completion of the n/s works. *Note: This is not a legal opinion and no liability for reliance on its contents attaches to the writer or sender. RACA See Administrator Natal v Magill, Grant & Nell (Pty) Ltd (In Liquidation) 1969 (1) SA 660 (A), 672B and discussion under bullet 4. 9 th Edtn, Juta, Feb 2007. See Minister of Public Works and Land Affairs v Group Five Building Ltd 1999 (4) SA 12 (AD) Refer dicta in BK Tooling (Edms) Bpk v Scope Precision Engineering (Edms) Bpk 1979 (1) SA 391 (A) generally at pp. 438-440. www.hvacronline.co.za RACA Journal I February 2020 65