RACA Journal February 2020 | Page 64

Contract savvy but it could relate to stock items not prematurely ordered where the supplier insists on and is entitled to a cancellation amount (say a bulk order for copper piping at a reduced price for bulk). NSSA clause 31.6 limits the ability to place orders for goods prematurely and without justification and provides a very good reason why subcontractors should ensure that the placing of such orders should be covered by notice to the employer and contractor and their agreement thereto even where it is necessary as part of a price fixing agreement. The subcontractor has a common law obligation to mitigate damage and may have to communicate with the contractor and employer on preference for a termination fee rather than specific performance because, in the event of a termination fee on a bulk order such as the example above, the contractor would be the party having to pay the damages for the termination [NSSA clause 38.5.6] whilst the employer may have to pay an increased cost for the balance of the goods if the initial order is terminated and then reclaim them as part of the costs of completing the works. The employer cannot forcibly or against the subcontractors will take over an order issued by the subcontractor – it would have to be by mutual agreement and interest. If the employer deals directly with the supplier and arranges for a termination of the subcontractor’s order and direct sale to the employer (inducement) there could be a case for wrongful interference by the employer 9 or wrongful termination by the supplier but inevitably such actions are more often than not avoided due to practical and financial reasons and a subcontractor would normally make use of its dispute resolution provisions to recover any funds due to it as part of its contractual entitlement. It is submitted that the value of materials and goods included in a paid interim certificate may be excluded from this provision 10 although this is extremely arguable if the subcontractor has not been paid by the contractor (see Concor Holdings (Pty) Ltd v Potgieter (219/03), [2004] ZASCA (28 May 2004); Administrator General South West Africa v Trust Bank of Africa Ltd 1982 (1) SA 635 (SWA) judgments). If uncontested by the subcontractor by the exercise of liens and reservation of ownership, the employer may lay claim to the materials and leave it to the subcontractor to prove a claim for materials and goods certified but not paid to the subcontractor, whatever the reason for such non-payment, but care would need to be exercised to not dispossess the subcontractor improperly and face a spoliation order. This is a double-edged sword because the employer would also be entitled to assert a claim against 9 See Neethling–Potgieter-Visser Law of Delict, 6 th Edtn, LexisNexis Durban 2010 pp. 306-307 and particularly p. 307 where the inducement causes a lawful termination of the contract. 10 Materials and goods included in a payment certificate become the property of the employer in terms of NSSA clause 31.6 62 RACA Journal I February 2020 www.hvacronline.co.za