Intersection improvements for St. Lucie West, NW Peacock boulevards
Roadway Resurfacing Projects
www. cityofpsl. com / repaving
The Capital Improvement resurfacing goal for FY 2024-25 is 21.68 miles with 9.83 miles completed to date. Residents will be notified in advance of resurfacing.
• Northport Village: Complete
• Cashmere Cove
• Palm Trails( Del Rio): Complete
• St. Lucie West( University): Complete
• Oak Hammock / Palm Trails( Savona): Complete
• Newport Isles: Scheduled
• Hidden Oaks: Complete
• Rosser Reserve / Woodland Trails( Paar Mid):
• Complete
• Sandpiper Bay( Mid)
• Sandpiper Bay( North): Under construction
• Riverview: Complete
Construction started in May for intersection improvements at St. Lucie West and NW Peacock boulevards. The City is adding lanes to St. Lucie West and Peacock boulevards to improve traffic flow and access to Interstate 95. The project will also enhance sidewalks, drainage and landscaping.
To help answer questions and inform residents and businesses about the project, the City hosted a public meeting May 5 at South County Regional Stadium. City staff and the project team were available to answer questions and provide information on the project.
Lane closures are anticipated throughout construction. Residents are asked to use caution as they drive through the area.
Raising money for Treasure Coast Food Bank
Public Works staffers Emily Seitter, Everett Tourjee, Christine Murphy and Valerie Delgado are Several Public Works staffers helped organize and play in the annual Treasure Coast Branch American Public Works Association( APWA) Golf Tournament, which helps the local branch raise money for events, scholarships and local charities. The local branch gives money each year to the Treasure Coast Food Bank.
Thanks to all those who played, sponsored and volunteered to support this annual event