Protection Engineering Basics and Schemes Protection Engineering | Page 113

We used these relays for motor protection and downstream protection. In motors, at time of motor starting, motor draw more current then normal current due to torque. We need to introduce time delay at the starting of motor. 5.3.2 Inverse Time Relay(51) These Relays are introduced on the principle of Time vs fault intensity. We follow simple rule here, if intensity of fault is high then Relay tripping time will be low. We called it Time current characteristics (TCC), TCC help us in Relay coordination We as per IEC have multiple TCCs      pg. 113 Normal or Standard Inverse Very inverse Extreme Inverse Long time earth Customized