PROJECT 19
Supplied by Greenfields Plumbing Design
The wheel-chair accessible showers.
The communal bathrooms.
Supplied by Greenfields Plumbing Design
Product Supplier Details Waste reticulation
50 – 160mm HDPE system
Water Reticulation
Geberit
Mepla Multilayer pipe system 16 – 75mm
diameter
Sanitaryware
Lecico
Atlas wall hung basins, with Atlas dual flush
close coupled WC suites
Brassware Plumline Lyra basin, shower and sink mixers Sunridge Borras Demorar Demand pillar taps STD #
BMMTP2 Stainless Steel Franke Projectline sinks and drip sinks
Heat Pumps
Greenbro
Six: 63kW RBG-630E / SN2-M air to water
heat pumps
Boilers
Greenbro
Six: 5 000l SA BOILER OPTIMA horizontal
hot water storage cylinders
Booster Pump
WCP( Western Cape Pumps)
( WCP 2 CR20 – 06) – 12.5l / s @ 6 Bar
pump set
Water Storage Roto Three: 5 500l Roto water storage tanks
Client Project Manager and Principal Agent Architect Green Consultant Quantity Surveyor Structural and Civil Engineer Mechanical, Electrical, WET Services and Fire Engineers Contractor Plumbing Contractor
Adowa Property Developers Threshold Project Managers( Pty) Ltd SVA International( Pty) Ltd Solid Green Rider Levett Bucknail( ZA)( Pty) Ltd Richard Ramplin Consulting( Pty) Ltd Richard Ramplin Consulting( Pty) Ltd Washrika 3 Oaks( Pty) Ltd Greenfields Plumbing Design
May 2026 Volume 32 I Number 03 www. plumbingafrica. co. za